Text Size: A+| A-| A   |   Text Only Site   |   Accessibility
 

Deliverable-based $0 - $5,000 PSK

Precondition

  • Business Case Methodology (MS Word
  • Approved decision to contract
  • Complete DHS Contract Request Form (DHS 0118) (MS Word) (PDF)
  • Develop Statement of Work (SOW) (MS PowerPoint)

Step

Action

OIS

OCP

Duration

 

PSK Process – contract need through Notice to Proceed

   

5 – 35 days

 

A

Develop Solicitation (optional - if no solicitation, go to Step B)

   

2 – 14 days

1

Develop plan to complete the Request for Proposal (RFP)

  • Step #1: Project Manager (PM) enters contract tasks into project schedule
  • Step #2: PM & Contracts Coordinator Agree on schedule commitments for contract tasks
Lead  

1 – 7 business days

2

Draft Contract

  • Step #1: Refine Statement of Work (SOW)
  • Step #2: Define milestones, tasks, deliverables, due dates
  • Step #3: Draft Contract Terms & Conditions
  • Step #4: Update project schedule (communication issue option)
Lead – Steps 1,2,4

Lead – Step 3

 

1 – 7 business days

B

Award Contract (if no solicitation, start here)    

3 – 28 days

1

Negotiate Contract Issues

  • Step #1: Identify and Negotiate Issues (limited to SOW, Milestones, Delivery Schedule, & Cost)
  • Step #2: Update Contract
Lead – Step 1

Lead – Step 2

Facilitate – Step 1

1-7 business days

7 - 14 business days if no solicitation

2

Coordinate Contract Review and Approvals

  • Step #1: Contractor approval
  • Step #2: OIS CIO or Deputy CIO approval
  • Step #3: Coordinate all revisions to Proposed Contract (if required)
  Lead

1 – 7 business days

 

3

Issue Notice to Proceed

  • Step #1: Issue Notice to Proceed to Contractor and notify OIS
  • Step #2: Notify program or business area Step #4:
  • Step #3: Issue Executed Copy of Contract to Contractor and OIS
Lead - Step 2

Lead – Steps 1, 3

1 – 7 business days



 

Glossary

  • Duration Estimates - Duration estimates are most likely for a formal contract, i.e., on average the task will be completed within that time frame. Shaded cells indicate durations for federal approval agency (if required).
  • Facilitate – Lead discussion and tasks that results in a completed product. Responsible for document version control. Collaborates with all stakeholders.
  • Lead – Primary ownership and responsibility to ensure the task is completed. Collaborates with all stakeholders.
  • Stakeholder – Individuals and/or groups who are involved in or may be affected by task activities.

Duration Estimates – Assumptions

Actual Duration will be affected by DHS’ priority, scope of the project and deliverables, solicitation strategy, issue resolution, and resource availability.

 

 
Page updated: September 21, 2007

Click here to go to the Oregon Dept. of Veterans' Affairs outreach contact form

Get Adobe Acrobat ReaderAdobe Reader is required to view PDF files. Click the "Get Adobe Reader" image to get a free download of the reader from Adobe.