Deliverable-based $5,000 - $75,000 PSK

Preconditions

  • Business Case Metholology (MS Word)
  • Approved decision to contract
  • Obtain Legislative approval (policy option package, JLCIMT, Eboard, Ways & Means if required)
  • Develop Statement of Work (SOW) (MS PowerPoint)
  • Complete IRR (MS Word)
  • Complete SEIU Feasibility Study (DHS 0117), if more than $30K in a calendar year (MS Word)
  • Complete DHS Contract Request Form (DHS 0118) (MS Word) (PDF)
  • Complete Advanced Planning Document (APD) for enhanced Federal Financial Participation (if required)
  • Obtain other funding source requirements (i.e., Grants, Department of Education, Department of Labor, etc, if required)

Step

Action

OIS

OCP

Duration

 

PSK Process – contract need through Notice to Proceed

   

33 – 110 days

58 – 336 days*

A

Develop Solicitation

   

15 – 47 days

15 – 137 days*

1

Develop plan to complete the Request for Proposal (RFP)

  • Step #1: Project Manager (PM) enters contract tasks into project schedule
  • Step #2: PM & Contracts Coordinator Agree on schedule commitments for contract tasks
Lead  

7 – 10 calendar days

2

Draft RFP

  • Step #1: Develop Statement of Business Need
  • Step #2: Refine SOW
  • Step #3: Define milestones, tasks, deliverables, due dates
  • Step #4: Define Proposal Requirements & Evaluation Criteria – Cost, Management (organization, staffing, key people), and technical (approach, WBS, schedule.)
  • Step #5: Draft Contract Terms & Conditions
  • Step #6: Update project schedule
  • Step #7: Update procurement schedule
Lead – Steps 1,2,3,6

Lead – Step 5

 

Facilitate – Step 4

7 – 30 calendar days

 

driven by agreement in step 1

3

Coordinate RFP Review & Approvals

  • Step #1: OIS & Business Management (if required)
  • Step #2: Federal Approval Agency (if required) – draft, informal review and a final, formal review and approval.
  • Step #3: Manage changes to RFP during reviews
Lead – Steps 1,2

Facilitate – Step 3

 

 

1 – 7 calendar days

 

add 90 days for CMS approval

B

Conduct and Evaluate Proposals

   

11 – 35 days

11 – 65 days*

1

Release RFP

  • Step #1: Facilitate question and answer period (optional)
  • Step #2: CMS Approval (if required).
  • Step #2: Publish RFP Amendments (if required)
  Lead

5 – 14 calendar days

30-60 days*

for CMS approval concurrent to B-1.1

2

Review Proposals

  • Step #1: Receive Proposals
  • Step #2: Responsiveness Review of Management, Technical, and Cost Proposals
  • Step #3: Issue Requests for Proposal Clarification and/or Rejection of Non-Responsive Proposals (if required)
  • Step #4: Evaluate Cost Proposals
  • Step #5: Organize Evaluation Team of three or more evaluators, establish roles & responsibilities, and deliver Proposal Evaluation Package
  • Step #6: Evaluation and Scoring
  • Step #7: Ranking & Notification
Lead – Steps 5,6

Lead – Steps 1,2,3,4,7


Facilitate – Steps 5,6

5 – 14 calendar days

3

Agency’s Decision

  • Step #1: Present recommendations to OIS Executive Staff & Business Management
  • Step #2: Decision to proceed or cancel based on OIS Authorization to proceed
  • Step #3: If proceed – then notify Proposers of Agency’s intent to award
  • Step #4: If cancel – then notify Proposers of Agency’s decision to cancel
  • Step #5: Begin federal approval agency informal draft review (if required)
Lead – Steps 1,2,5

Lead – Steps 3,4

1 – 7 calendar days (Steps 1-4)

 

add 30 days concurrent to C1 & C2 for federal review (Step 5)

C

Award Contract    

7 – 28 days

7 – 88 days*

1

Negotiate Contract Issues

  • Step #1: Identify and Negotiate Issues (limited to SOW, Milestones, Delivery Schedule, & Cost)
  • Step #2: Update Contract
Lead – Step 1

Lead – Step 2

Facilitate – Step 1

5-14 calendar days

2

Coordinate Contract Review and Approvals

  • Step #1: Contractor approval
  • Step #2: OIS CIO or Deputy CIO approval
  • Step #3: Budgetary Authority (if budget is outside OIS)
  • Step #4: Federal Approval Agency (if required) – formal review and approval. Must be accompanied by appropriate documentation (i.e., APD Update for CMS approval).
  • Step #5: Coordinate all revisions to Proposed Contract (if required)
Lead – Step 4 (APD Update for CMS approval)

Lead

1 – 7 calendar days

 

add 60 days for CMS approval

Steps 1-4 may be concurrent

3

Issue Notice to Proceed

  • Step #1: Issue Notice to Proceed to Contractor and notify OIS
  • Step #2: Notify program or business area
  • Step #3: Issue Executed Copy of Contract to Contractor, OIS, and Federal Approval Agency
Lead - Step 2

Lead – Step 1,3

1 – 7 calendar days



 

Glossary

  • ACF – Administration for Children and Families [United States Department of Health & Human Services (USDHHS)].
  • CMS – Centers for Medicare & Medicaid Services [United States Department of Health & Human Services (USDHHS)].
  • Duration Estimates - Duration estimates are most likely for a formal contract, i.e., on average the task will be completed within that time frame. Shaded cells indicate durations for federal approval agency (if required).
  • Facilitate – Lead discussion and tasks that results in a completed product. Responsible for document version control. Collaborates with all stakeholders.
  • FNS – Food and Nutrition Services [United States Department of Agriculture (USDA)].
  • IRR – Information Resource Request is sent to DAS - Information Resources Management Division.
  • Lead – Primary ownership and responsibility to ensure the task is completed. Collaborates with all stakeholders.
  • Stakeholder – Individuals and/or groups who are involved in or may be affected by task activities.

Duration Estimates – Assumptions

  • Actual Duration will be affected by DHS’ priority, scope of the project and deliverables, solicitation strategy, issue resolution, and resource availability.
* The second date range includes the timeframe for CMS review and approval.

 

 