Text Size: A+| A-| A   |   Text Only Site   |   Accessibility
 

Deliverable-based $75,000 and above PSK

Preconditions

  • Business Case Methodology (MS Word)
  • Approved decision to contract
  • Obtain Legislative approval (policy option package, JLCIMT, Eboard, Ways & Means)
  • Develop Statement of Work (SOW) (MS PowerPoint) 
  • Complete DAS IRMD Business Case & Feasibility Study (MS Word) also see DAS IRMD IT Policy Requirements
  • Complete DAS IRMD Cost Benefit Analysis & IRR (MS Word)
  • Complete SEIU Feasibility Study (DHS 0117) (MS Word)
  • Complete DHS Contract Request Form (DHS 0118) (MS Word) (PDF)
  • Complete Advanced Planning Document (APD) for enhanced Federal Financial Participation (if required)
  • Obtain other funding source requirements (i.e., Grants, Department of Education, Department of Labor, etc, if required)

Step

Action

OIS

OCP

Duration

 

PSK Process – contract need through Notice to Proceed

   

138 – 378 days

138 – 558 days*

A

Develop Solicitation

   

52 – 130 days

52 – 220 days*

1

Develop plan to complete the Request for Proposal (RFP)

  • Step #1: Project Manager (PM) enters contract tasks into project schedule
  • Step #2: PM & Contracts Coordinator Agree on schedule commitments for contract task
Lead  

7 – 10 calendar days

2

Draft RFP

  • Step #1: Develop Statement of Business Need
  • Step #2: Refine SOW
  • Step #3: Define milestones, tasks, deliverables, due dates
  • Step #4: Define Proposal Requirements & Evaluation Criteria – Cost, Management (organization, staffing, key people), and technical (approach, WBS, schedule.)
  • Step #5: Draft Contract Terms & Conditions
  • Step #6: Update project schedule
  • Step #7: Update procurement schedule
Lead – Steps 1,2,3,6

Lead – Step 5

 

Facilitate – Step 4

30 – 90 calendar days

 

driven by agreement in step #1

3

Coordinate RFP Review & Approvals

  • Step #1: OIS & Business Management (if required)
  • Step #2: DOJ (if required)
  • Step #3: DAS (if required)
  • Step #4: Federal Approval Agency (if required) – draft, informal review and a final, formal review and approval.
  • Step #5: Manage changes to RFP during reviews
Lead – Steps 1,4

Facilitate – Step 5

 

Lead – Steps 2,3

15 – 30 calendar days

 

add 90 days for CMS approval

B

Conduct and Evaluate Proposals

   

51 – 134 days

51 – 164 days*

1

Release RFP

  • Step #1: Facilitate question and answer period
  • Step #2: Facilitate pre-proposal vendors’ conference (if required)
  • Step #3: Resolution of solicitation protests (if required)
  • Step #4: CMS Approval (if required)
  • Step #5: Publish RFP Amendments (if required
  Lead

30 – 60 calendar days

30-60 days*

for CMS approval concurrent to

B-1.3

2

Review Proposals

  • Step #1: Receive Proposals
  • Step #2: Responsiveness Review of Management, Technical, and Cost Proposals
  • Step #3: Issue Requests for Proposal Clarification and/or Rejection of Non-Responsive Proposals
  • Step #4: Organize Evaluation Team, establish roles & responsibilities, and deliver Proposal Evaluation Package
  • Step #5: Evaluation and scoring
  • Step #6: Ranking & Notification
Lead – Steps 4,5

Lead – Steps 1,2,3,6


Facilitate – Steps 4,5

14 – 60 calendar days

3

Agency’s Decision

  • Step #1: Present recommendations to OIS Executive Staff & Business Management
  • Step #2: Decision to proceed or cancel based on OIS Authorization to proceed
  • Step #3: If proceed – then notify Proposers of Agency’s intent to award
  • Step #4: If cancel – then notify Proposers of Agency’s decision to cancel
  • Step #5: Resolution of Award Protest issues (if required)
  • Step #6: Begin federal approval agency informal draft review (if required
Lead – Steps 1,2,6

Lead – Steps 3,4,5

7 – 14 calendar days (Steps 1-4)

add time for award protest (Step 5)

add 30 days concurrent to C1 & C2 for federal review (Step 6)

C

Award Contract    

35 – 114 days

35 – 174 days*

1

Negotiate Contract Issues

  • Step #1: Identify Negotiation Team Members and establish roles & responsibilities (may include external partners, i.e., DOJ)
  • Step #2: Identify and Negotiate Issues (limited to SOW, Milestones, Delivery Schedule, & Cost)
  • Step #3: Develop Contract Administration Plan
  • Step #4: Update Contract
Lead – Steps 1,2,3

Lead – Step 4

 

Facilitate – Steps 1,2

14-60 calendar days

2

Coordinate Contract Review and Approvals

  • Step #1: OIS, Business Management, and Proposer Initial Review
  • Step #2: DOJ approval (if required)
  • Step #3: DAS/IRMD approval (if required)
  • Step #4: OIS CIO or Deputy CIO approval
  • Step #5: Contractor approval
  • Step #6: Budgetary Authority (if budget is outside OIS)
  • Step #7: Federal Approval Agency (if required) – formal review and approval. Must be accompanied by appropriate documentation (i.e., APD Update for CMS approval).
  • Step #8: DAS State Procurement Office (SPO)
  • Step #9: Coordinate all revisions to Proposed Contract (if required)
Lead – Step 7 (APD Update for CMS approval)

Lead - Steps 1,2,3,4,5,6,
8,9

14 – 40 calendar days

 

add 60 days for CMS approval

 

steps 4-7 may be concurrent

 

3

Issue Notice to Proceed

  • Step #1: Receive Executed Contract from DAS Procurement
  • Step #2: Request to Contractor for Insurance Certification/Execution of Bonds (if any)
  • Step #3: Issue Notice to Proceed to Contractor and notify OIS
  • Step #4: Notify program or business area
  • Step #5: Issue Executed Copy of Contract to Contractor, OIS, and Federal Approval Agency
Lead - Step 4

Lead – Steps 1, 2, 3, & 5

7 – 14 calendar days



 

Glossary

  • ACF – Administration for Children and Families [United States Department of Health & Human Services (USDHHS)].
  • CMS – Centers for Medicare & Medicaid Services [United States Department of Health & Human Services (USDHHS)].
  • Duration Estimates - Duration estimates are most likely for a formal contract, i.e., on average the task will be completed within that time frame. Shaded cells indicate durations for federal approval agency (if required).
  • Facilitate – Lead discussion and tasks that results in a completed product. Responsible for document version control. Collaborates with all stakeholders.
  • FNS – Food and Nutrition Services [United States Department of Agriculture (USDA)].
  • IRR – Information Resource Request is sent to DAS - Information Resources Management Division.
  • Lead – Primary ownership and responsibility to ensure the task is completed. Collaborates with all stakeholders.
  • Stakeholder – Individuals and/or groups who are involved in or may be affected by task activities.

Duration Estimates – Assumptions

  • Actual Duration will be affected by DHS’ priority, scope of the project and deliverables, solicitation strategy, issue resolution, and resource availability.
* The second date range includes the timeframe for CMS review and approval.

 

 
Page updated: September 21, 2007

Click here to go to the Oregon Dept. of Veterans' Affairs outreach contact form

Get Adobe Acrobat ReaderAdobe Reader is required to view PDF files. Click the "Get Adobe Reader" image to get a free download of the reader from Adobe.