| Piling Placement or Removal |
 |
|
 |
|
|
|
|
Pilings along Siuslaw River photo Chris Castelli
|
General Authorization for Piling Placement or Removal
To be eligible for this General Authorization, the project must be for the purpose of placing or removing piling in waters of the state for over-water structure support or navigational aid.
The project must meet the following criteria:
- Involve placement of no more than five piles or one dolphin that consists of three to five piles
- Consist of untreated wood, steel, fiberglass or plastic piles
- Be fitted with devices to prevent perching by fish-eating birds
- Be placed from a barge-mounted or above top-of-bank position. If placed by barge, the barge shall not be grounded on the bed or banks.
- Be placed by means of impact or vibratory methods
- Be removed by vibratory methods only
The following projects are NOT eligible for this authorization:
- Projects using piling to construct headwalls or other bank treatment structures
- Projects using piling to create new uplands
- Projects using sheetpile
- Pilings placed or removed by excavation
- Projects where piling is placed in wetlands or placed to impede normal water flow into or within wetlands or placed in a manner to cause erosion
- Pilings that interfere with or create hazards to recreational or commercial navigation
- Pilings placed as poured-in-place concrete
- Projects including placement of footings or other support structures for the piling
To apply, complete an application for a General Authorization for Piling Placement or Removal.
For a more detailed description of additional eligibility and mandatory requirements, consult OAR 141-089-0400-0430. (At Secretary of State site, press CTRL-F, key in 00400, and press Enter)
If you have further questions about a specific project, contact the DSL Resource Coordinator for your county.
|
|
|
|