| Helix Wind Power Facility |
|
|
 |
|
|
Facility: Wind energy facility with up to 60 wind turbines and a combined peak generating capacity of not more than 102 megawatts.
Location: Umatilla County.
Status:
The Council has issued a site certificate.
Certificate Holder:
Iberdrola Renewables, Inc.
Contact:
Sara McMahon Parsons
Iberdrola Renewables, Inc.
1125 NW Couch Steet, Suite 700
Portland, OR 97209
(503) 796-7732
Department of Energy Staff: John White
Original site certificate signed: (pending)
History:
- August 12, 2008: Applicant submitted a Preliminary Application.
- March 10, 2009: Date of filing (application complete).
- May 5, 2009: Department of Energy issued a Draft Proposed Order.
- June 17, 2009: Department of Energy issued a Proposed Order.
- July 31, 2009: Council issued a Final Order approving a Site Certificate.
Documents:
-
Attachment A (Wildlife Monitoring and Mitigation Plan) [149 kb pdf]
-
|
|
|
|