Port Westward Generating Project
|
|
|
Article Content
|
 |
|
|
Facility:
650 MW natural gas combined-cycle combustion turbine system
Location: Columbia County
Status:
Operating since July 19, 2007.
Certificate Holder:
Portland General Electric Company
Contact:
Arya Behbehani-Divers
Portland General Electric Company
121 SW Salmon Street
Portland OR 97204
503-464-8141
Department of Energy staff: Duane Kilsdonk
Original site certificate signed: November 12, 2002
Current site certificate: Seventh Amended Site Certificate (pending)
History:
-
February 27, 2001: Notice of intent submitted.
-
April 28, 2001: Department of Energy issued a project order.
-
August 16, 2001: Application submitted.
-
November 5, 2001: Department of Energy issued an amended project order.
-
April 11, 2002: Application complete (date of filing).
-
June 26, 2002: Department of Energy issued a draft proposed order.
-
August 1, 2002: Public hearing held in Clatskanie, Oregon.
-
August 23, 2002: Department of Energy issued a proposed order.
-
August 26, 2002: Contested Case Notice.
-
November 8, 2002: Council approved a site certificate.
-
September 25, 2003: Request for Amendment #1 received.
-
December 5, 2003: Council approved Amendment #1.
-
May 7, 2004: Request for Amendment #2 received.
-
August 10, 2004: Department issued a proposed order on Amendment #2.
-
September 24, 2004: Council approved Amendment #2.
-
December 16, 2004: Department issued a proposed order on Amendment #3.
-
January 28, 2005: Council approved Amendment #3.
-
February 14, 2005: Construction begun.
-
January 17, 2006: Request for Amendment #4 received.
-
February 6, 2006: Department issued a proposed order on Amendment #4.
-
February 10, 2006: Council approved Amendment #4.
-
May 19, 2006: Council issued a final order on Amendment #4.
-
July 20, 2006: Request for Amendment #5 received.
-
August 22, 2006: Department issued a proposed order on Amendment #5.
-
September 20, 2006: Council approved Amendment #5.
-
November 7, 2008: Request for Amendment #6 received.
-
February 23, 2009: Department issued a proposed order on Amendment #6.
-
March 27, 2009: Council approved Amendment #6.
-
September 18, 2009: Request for Amendment #7 received.
-
January 13, 2010: Department issued a proposed order on Amendment #7.
-
March 12, 2010: The Council approved Amendment #7.
-
November 4, 2010: Request for Amendement #8 received.
-
January 5, 2011: Department issued a Draft Proposed Order on Amendment #8.
-
June 9, 2011: Department issued a Proposed Order on Amendment #8
Documents:
-
Site Certificate, November 2002
-
Final Order on Amendment #1, December 2003
-
First Amended Site Certificate, December 2003
-
Final Order on Amendment #2, September 2004
-
Second Amended Site Certificate, September 2004
-
Final Order on Amendment #3, January 2005
-
Third Amended Site Certificate, January 2005
Attachment A: Monetary Path Payment Requirement
Attachment A1: Monetary Path Payment Requirement with Standby Letter of Credit
Attachment B-1: Proposed Water Pollution Control Facilities Permit
Attachment B-2: Onsite WPCF Permit Evaluation
Attachment C-1: Proposed Removal/Fill Permit
Attachment C-2: Special Conditions for Removal/Fill Permit
-
Temporary Order on Amendment #4, February 2006 [71 kb pdf]
-
Final Order on Amendment #4, May 2006 [113 kb pdf]
-
Fourth Amended Site Certificate, May 2006 [260 kb pdf]
-
Request for Amendment #5, July 2006 [78 kb pdf]
Figure 1 [684 kb pdf]
Figure 2 [386 kb pdf]
-
Final Order on Amendment #5, September 2006 [60 kb pdf]
-
Fifth Amended Site Certificate, September 2006 [168 kb pdf]
-
Request for Amendment #6, November 2008 [231 kb pdf]
-
Sixth Amended Site Certificate, March 2009[210 kb pdf]
-
Proposed order on Amendment #7, January 2010 [321 kb pdf]
-
Final Order on Amendment 7 [777 kb pdf]
-
Request for Amendment #8, November 4, 2010
-
Draft Proposed Order on Amendment #8, January 2011 [295 kb PDF]
-
Proposed Order on Amendment #8, January 2011 [466 kb PDF]
|
|
|
|
|
|
|
|
|
|
|