| South Mist Pipeline Extension |
|
|
 |
|
|
Facility:
62 mile, 24-inch natural gas pipeline
Location: Washington, Clackamas and Marion Counties
Status: Operating.
Certificate Holder:
Northwest Natural
Contact:
Gary Bauer
Northwest Natural
220 NW Second Ave.
Portland OR 97209
503-220-2403
Department of Energy staff: Adam Bless
Original site certificate signed: March 21, 2003
Current site certificate: Fourth Amended Site Certificate (issued July 27, 2007)
History:
- September 30, 1999: Notice of intent submitted
- March 29, 2000: Department of Energy issued a project order
- March 22, 2001: Application submitted
- September 24, 2001: Application complete (date of filing)
- July 10, 2002: Department of Energy issued a draft proposed order.
- September 19, 2002: Department of Energy issued a proposed order.
- March 13, 2003: Council approved a site certificate
- June 5, 2003: Request for Amendment #1 received.
- July 11, 2003: Department of Energy issued proposed order on Amendment #1
- August 28, 2003: Council approved Amendment #1
- September 12, 2003: Request for Amendment #2 received
- September 30, 2003: Department of Energy issued a proposed order on Amendment #2
- October 8, 2003: Council approved Amendment #2 (temporary order)
- December 5, 2003: Council adopted a final order on Amendment #2
- February 18, 2004: Request for Amendment #3 received
- March 19, 2004: Department of Energy issued a proposed order on Amendment #3
- April 23, 2004: Council approved Amendment #3
- April 25, 2007: Request for Amendment #4 received.
- June 22, 2007: Department of Energy issued a proposed order on Amendment #4
- July 27, 2007: Council approved Amendment #4.
Documents:
- Final Order on the Site Certificate
Attachment A: Land Use Analysis of Local Requirements
Attachment B: Compliance with ORS Chapter 215.275 Analysis
Attachment C: Proposed Order, Issued September 19, 2002
Attachment D: Revised Agricultural Impact Mitigation Plan
- Site Certificate, March 2003
- First Amended Site Certificate, August 2003
- Second Amended Site Certificate, December 2003
- Final Order on Amendment #3, April 2004
- Third Amended Site Certificate, April 2004
- Request for Amendment #4, April 2007 [129 kb pdf]
- Final Order on Amendment #4, July 2007 [168 kb pdf]
- Fourth Amended Site Certificate, July 2007 [200 kb pdf]
|
|
|
|