Text Size: A+| A-| A   |   Text Only Site   |   Accessibility
ODOT Banner Image
February 2007
February 1
February 15
February 22
February 1
Notice to Contractors
3 week ad
 

Addendum Letters
1. HCRH Interpretive Sites and Signs Section
          Addendum Letter No. 1- Janauary 19, 2007
 
2.  I-84: Sandy River - The Dalles (Fencing) Project
          Addendum Letter No. 1 - January 17, 2007
            Postponement Letter - January 23, 2007 - will re-advertise with new documents
                                                                                   at a later date
3.  Oak St - McAndrews to Taft Section
          Addendum Letter No. 1 - January 19, 2007
          Addendum Letter No. 2 - January 24, 2007 - Postponed to February 1, 2007
          Addendum Letter No. 3 - January 25, 2007

Plan Holders List
List of Prime and Sub Contractors
 

Post Bid Information
Bid Tabulations
 

February 15
Notice to Contractors
3 week ad
 

Addendum Letters
1.  OR126: Durable Striping Section
          Addendum Letter No. 1 - February 7, 2007
 
2.  OR233: Johnson Creek Culvert Section
          Addendum Letter No. 1 - February 8, 2007
 
3.  I-5: S Wolf Creek - Foothills Blvd - Bundle 303 Section
          Addendum Letter No. 1 - January 29, 2007
          Addendum Letter No. 2 - February 9, 2007

Plans Holders List
List of Prime and Sub Contractors
 

Post Bid Information
Bid Tabulations

February 22
Notice to Contractors
3 week ad
 

Addendum Letters
1.  OR335 @ Adams Intersection & Greasewood Creek Bridge Section
          Addendum Letter No. 1 - February 7, 2007
          Addendum Letter No. 2 - February 14, 2007
          Addendum Letter No. 3 - February 15, 2007 - Postponed until March 29, 2007
 
2.  US97: China Hat Rd - Baker Rd/Lava Butte Section
          Addendum Letter No. 1 - February 8, 2007
 
3.  US20: Hampton to Glass Butte Preservation Section
          No Addendum Letters
 
4.  I-5: Azalea to Glendale Reconstruction Section
          Addendum Letter No. 1 - February 13, 2007
 
5.  OR82: Riddle Road (La Grande) - Imber Section
          Addendum Letter No. 1 - February 7, 2007
          Addendum Letter No. 2 - February 14, 2007
 

Plan Holders List
List of Prime and Sub Contractors
 

Post Bid Information
Bid Tabulations

 
Page updated: December 21, 2007

Click here to go to the Oregon Dept. of Veterans' Affairs outreach contact form

Get Adobe Acrobat ReaderAdobe Reader is required to view PDF files. Click the "Get Adobe Reader" image to get a free download of the reader from Adobe.