| May 8 |
|
Notice to Contractors
3 week ad
Addendum Letters
1. Rogue River Parkway to Creel Road Section
Addendum Letter No. 1 - May 1, 2008
2. I-84: Sandy River Delta Access Section
Addendum Letter No. 1 - April 22, 2008
Addendum Letter No. 2 - April 24, 2008
Addendum Letter No. 3 - May 1, 2008
3. Region 2 Pavement Markers (2008) Section
No Addendum Letters
4. 69th Street: Thruston Road - B Street (Springfield) Section
Addendum Letter No. 1 - May 2, 2008
5. US199: Rogue Community College - Midway Ave Section
Addendum Letter No. 1 - April 30, 2008
6. OR223 @ Washington St Signal Replacement (Dallas) Section
Addendum Letter No. 1 - April 17, 2008
Addendum Letter No. 2 - April 22, 2008 - Postponed until May 8, 2008
Addendum Letter No. 3 - May 1, 2008
Clarification Letter No. 1 - April 17, 2008
Plan Holders List
List of Prime and Sub Contractors
|
|
|
|
|
|
|
|
|
|
|