June 2011
|
|
|
|
|
|
Article Content
 |
| June 23 |
|
Notice to Contractors
3 week ad
Addendum Letters
1. Canaan Road Guardrail Section
No Addendum Letters
2. Region 5 Rockfall Corrections 2011 Section
Addendum Letter No. 1 - June 15, 2011
Addendum Letter No. 2 - June 16, 2011
3. Salmonberry Bridge Section
Addendum Letter No. 1 - June 16, 2011
Clarification Letter No. 1 - June 16, 2011
Clarification Letter No. 2 - June 20, 2011
4. OR224: I-205 - UPRR O'Xing WB Right Turn Lane Section
Addendum Letter No. 1 - June 10, 2011
Addendum Letter No. 2 - June 17, 2011
5. US101: Yaquina Bay Bridge #01820 Repair Projects
Addendum Letter No. 1 - June 8, 2011
Addendum Letter No. 2 - June 16, 2011
Clarification Letter No. 1 - June 16, 2011
6. Daggett Ln: Wells Acres Rd - Moonlight Dr (Bend)
Addendum Letter No. 1 - May 25, 2011
Addendum Letter No. 2 - June 7, 2011 - Postponed See June 23, 2011
Addendum Letter No. 3 - June 7, 2011
Plan Holders List
List of Prime and Sub Contractors
|
|
 |
| June 30 |
|
Notice to Contractors
3 week ad
Addendum Letters
1. Eureka Ave Sidewalk & Srts Pedestrian Crossings (Silverton)
Addendum Letter No. 1 - June 22, 2011
Addendum Letter No. 2 - June 23, 2011
Addendum Letter No. 3 - June 29, 2011 - Postponed See July 14, 2011
2. 82nd Ave/Columbai Intersection Improvements Section
Addendum Letters No. 1 - June 17, 2011
Addendum Letters No. 2 - June 24, 2011
Addendum Letters No. 3 - June 24, 2011
3. Heceta Head Lighthouse Restoration Section
Addendum Letters No. 1 - June 16, 2011
Addendum Letters No. 2 - June 23, 2011
Addendum Letters No. 3 - June 24, 2011
Clarification Letter No. 1 - June 21, 2011
Clarification Letter No. 2 - June 27, 2011
Approved Bidders
Pre-Bid Meeting Attendees
Plan Holders List
List of Prime and Sub Contractors
|
|
|
|
|
|
|
|
|
|
|