Erosion and Sediment Control
Cape Cove Slide Repair

The goal of project erosion & sediment control is to prevent pollution of water resources as required by National Pollutant Discharge Elimination System permits and by other laws, permits, agencies and agreements. 
Project Design Objectives include:

  • Establish specific measures to prevent soil erosion and off-site sedimentation
  • Satisfy permit requirement for an Erosion & Sediment Control Plan (ESCP)
  • Create clear contract documents to facilitate project construction
  • Minimize project and permit problems for ODOT and project partners