#4 Central Oregon Highway Bridges (COHB) - Bundle 102 - Region 5
 
Location:  US20
Design-Builder:  Wildish Standard Paving Co.
Design Firm:  David Evans & Associates (DEA)
Award Date:  March 10, 2004
Contract Amount:  $25,626,424
Specified Contract Completion Date:  June 30, 2006
Actual Contract Completion Date:  April 3, 2006
 
The Central Oregon Highway Bridges Design-Build project replaced sixteen (16) bridges and completed roadway realignment work on US Highway 20 in Central Oregon.  Three of the bridges were replaced as part of the statewide OTIA III Bridge Program.  This project also included new roadway alignment work at Jonesboro which eliminated a dangerous curve along the Malheur River.
 
This was the first corridor level Design-Build project in Oregon with the sixteen (16) bridges located along a 140.9 mile section of Highway 20.
 
Final Exemption Report (5/9/07)
Final FFE (08/04/03) 
 
For more information abouto this project contact:
Steve Narkiewicz, ODOT Consultant Project Manager @ (503) 986-3971 or by Email at:
 

 