Project Description

CM/GC Contracts Awarded

CM/GC Procurement Documents

 

 

Project Description

The I-5: Willamette River Bridge (Lane County), Bundle 220, project is being delivered using the CM/GC alternative contracting method.
 
This project proposes to replace the existing (decommissioned) 1,800-foot long bridge on I-5 over the Willamette River in Lane County.  A 1,993-foot long detour bridge over the Willamette River was constructed in 2003/2004 just east (upstream) of the existing bridge, after which the existing bridge was decommissioned.  In addition to crossing the Willamette River, the decommissioned bridge and the detour bridge both cross pedestrian paths on both sides of the river, Franklin Boulevard, two Union Pacific Railroad (UPRR) tracks, and the NB I-5 to WB Franklin Boulevard off-ramp.  Approximately 600 feet north of the decommissioned bridge is an existing 100-foot long bridge over the Canoe Canal that will also be replaced as part of this project. 
 
The new bridge will be constructed at the same location as the existing bridge, but will require roadway alignment adjustments in the immediate project area as the bridge design dictates.  The new bridge will be designed to eventually carry up to six (6) lanes of traffic to accommodate the 20-year design for future traffic needs. 
 
For more project-specific information, contact Jim Cox, OTIA III Bridge Delivery Unit Manager, at (503) 986-6612, or by email at:  mailto:%20Jim.B.Cox@odot.state.or.us


Additional project information can also be viewed on the ODOT Region 2 website at:  I-5: Willamette River Bridge  and the OBDP OTIA III project site at:  OTIA III - I-5: Willamette River Bridge, Bundle 220

 
CM/GC CONTRACTS AWARDED
 
I-5 Willamette River Bridge - Bundle 220
 
On May 7, 2008, ODOT awarded the A&E Contract for the I-5: Willamette River Bridge project to:
 
OBEC Consulting Engineers
Eugene, Oregon
Contract Amount:  $10,963,672.00
 
On June 17, 2008. ODOT awarded the CM/GC Contract for Pre-construction Phase Services on the I-5: Willamette River Bridge project to:
 
Hamilton Construction Company
Springfield, Oregon
Contract Amount: $2,291,299.00
 
For information regarding either the A&E or CM/GC Contracts, please contact Jim Cox, OTIA III Bridge Delivery Unit Manager, at (503) 986-6612, or by email at:  Jim.B.Cox@odot.state.or.us

 
CM/GC Procurement Documents
THE PROCUREMENT DOCUMENTS USED ON THE I-5: WILLAMETTE RIVER BRIDGE, CM/GC PROJECT ARE POSTED BELOW:
 
REQUEST FOR PROPOSALS (Released January 25, 2008)
 
RFP Forms  
      CM/GC Fee Form
 
The mandatory Pre-Proposal Meeting was held on February 8, 2008, from 10:00 am to 12:00 pm, in Salem, Oregon.  The list of all attendees and the notice of firms submitting a Letter of Interest, are below:
                   Mandatory Pre-Proposal Meeting Notice
                   Pre-Proposal Attendee List
                   Letters of Interest Recieved
 
Questions & Answsers / RFP Addendums
 
ADDENDUMS
 
2-13-08:  Addendum No. 1 to the CM/GC RFP
                Affected Documents:     1.  CM/GC Instructions to Proposers
                                                   2.  Exhibit G to the Sample CM/GC Contract
 
2-20-08:  Addendum No. 2 to the CM/GC RFP
                Affected Documents:     1.  RFP Forms Index
                                                   2.  OTC Proposal Bond Form (new)
                                                   3.  CM/GC General Provisions Section 00146 (new)
 
2-22-08:  Addendum No. 3 to the CM/GC RFP
                Affected Documents:     1.  CM/GC Instructions to Proposers
                                                   2.  CM/GC General Provisions Section 00146 (revised)
 
2-29-08:  Addendum No. 4 to the CM/GC RFP
                Affected Documents:     1.  CM/GC Instructions to Proposers
                                                   2.  CM/GC Sample Contract (page 13 only) 
                                                   3.  Exhibits to CM/GC Sample Contract (page 1 only)
                                                   4.  Exhibit H to the Sample CM/GC Contract (new)
                                                   5.  CM/GC General Provisions (page 10 only)
 
3-05-08:  Addendum No. 5 to the CM/GC RFP (Final )
                Affected Documents:     1. CM/GC Sample Contract (page 14 only)
                                                   2. Exhibit H to the Sample CM/GC Contract   (Revised)
 
 
QUESTIONS & ANSWERS 
 
3-12-08:  Question & Answer No. 6  ( Final )
 
Public Proposal Opening
 
The Public Proposal Opening of all Proposals received in response to the RFP issued on January 25, 2008 was held on March 14, 2008 at 2:30 PM PDT.  The opening results are posted below:
 
                   Public Proposal Opening Results  (.pdf) 3-18-08
 
EXEMPTION ORDER
  1. DRAFT Findings of Fact (FFE)  (.pdf) 7-13-07
  2. FFE Public Hearing Notice (.pdf) 7-13-07
  3. Final Findings of Fact (FFE) (.pdf) 8-23-07
  4. Draft Findings of Fact (FFE) - Amendment #1  (.pdf) 10-15-07
  5. FFE Amendment #1 - Public Hearing Notice   (.pdf) 10-15-07
  6. Amended Order 2007-51 (.pdf)  12-20-07