Text Size: A+| A-| A   |   Text Only Site   |   Accessibility
ODOT Logo
I-205 Preservation: Phase 2

 
 
 
 
Phase 2 Project Summary: A one year project to repair and pave Interstate 205 in Portland between Harold Street and the Columbia River.  See map of project area.  I-205 Preservation Phase 1(Oregon City to Harold St.) is substantially complete.
Status and Timeline: Construction began April 2005.  Work should be complete summer 2006.
Latest information:
(June 2006)
Finish work is taking place on the project through summer 2006. 
 
Polyester polymer concrete product has been applied to bridges in this project - for the first time in Oregon.  Read more about polyester polymer.
 
 
 

Project Information
I-205 between the Willamette and Columbia rivers is cracked and badly rutted from decades of use by heavy traffic. Average daily traffic volumes range from 146,200 at the northern end to 106,300 at the southern end. The Oregon Department of Transportation (ODOT) is concentrating its efforts on improving roadway safety by maintaining and preserving our existing system.
 
I-205 Preservation Project Phase 1  between Oregon City and Harold Street in Portland is complete.
 
I-205 Preservation Project Phase 2 between Harold Street in Portland and the Columbia River began construction April 2005. Work on two additional structures south of the main project corridor has been incorporated into this phase for the sake of efficiency.  The project is substantially complete with some signage and striping work continuing into summer 2006.  See the map below of the Phase 2 project area.
 
Phase 2 will repair and pave the concrete roadway and the bridge structures within the areas shown on the project map. It also will include installation of concrete barrier, signing upgrades and replacement of traffic signal and ramp meter loop detectors. New, brighter durable striping will mark out the lanes, ramps and shoulders.
 
The central portion of the project runs through the cities of Portland and Maywood Park.
 

Map Locations
1. (I-205 from Columbia River to Harold Street):
An asphalt concrete overlay will be applied to I-205 from Harold Street to the Columbia River.  All structures in this section will have a polyester polymer concrete applied and their bridge joints replaced.  Both overlays are to combat rutting caused by studded tires.  Durable striping and delineators will be used as additional safety features.  Concrete barrier and guardrail will be updated or added where needed.  Signs will be replaced and sign structures will be upgraded as needed.
 
2. (I-205 in Oregon City):
Sign bridges on Hwy 99E at Dune St. and the northbound I-205 ramp intersection will be replaced.  Signs on the I-205 Abernethy Bridge will be replaced.
 
3.   (I-205 at Tualatin River Bridge):
There are two bridge structures that carry the north and southbound freeway traffic over the Tualatin River.  These bridges will be reviewed for significant deterioration and either one, or both decks will have a polyester polymer concrete overlay applied.  The bridge rails will be replaced and upgraded to current safety standards.  Portions of the guardrail will be replaced.
 
Polyester Polymer
In Phase 1 of the I-205 Preservation Project, the resurfacing of the bridge structures prompted a three to four month closure of two on-ramps to the freeway. The motoring public adapted to the detour routes while the microsilica concrete overlay had time to cure.
 
In Phase 2, early designs required two detours and ramp closures of a similar nature. As major detour routes were considered, the project team worked to develop alternatives including a quicker curing overlay product.
 
Many hours of research and discussion followed. As a result of this work, it is exciting to report that the proposed multi-month long detours will be greatly reduced. Some lane restrictions and overnight ramp closures will still be required, but traffic impacts won’t be nearly as significant.
 
Research showed excellent results from other states using a polyester polymer concrete with a three-hour cure time. This process will now be used on the Phase 2 project.  ODOT will use polyester polymer concrete on all seven of the structures requiring resurfacing.
 
View photos of polyester polymer being used on the project.

Construction Schedule & Noise
Much of this work will take place at night. ODOT has received noise variance from nighttime noise ordinances for this construction from the Cities of Portland, West Linn, and Maywood Park.
 
Though work will be conducted during the day on the project, the use of nighttime construction is critical in order to maintain traffic flow on this major interstate freeway.  Currently, the highway functions at capacity. This means there is little room for more traffic. Closing lanes for daytime construction could cause severe traffic congestion.
 
Nighttime construction noise may be audible to residents living along the project corridor. However, noise levels dissipate quickly as distance from the source increases. The paving operation is continually moving. Though construction work may still be audible at 400 feet, its decibel level will be the same as or very similar to existing traffic noise levels.
 
ODOT will keep those nearest the work notified of nighttime, noise-generating activities. A phone number is available for reporting noise problems requiring immediate attention (see below).

ODOT Contact Information
  • Judy Shioshi, ODOT Community Affairs: 503-731-8237
  • To leave a message for a return call (24 hours/day): 503-731-4128
  • TTY 503-735-2900
  • To report noise problems or incidents requiring immediate attention: 503-412-2352
 
¿Habla ustéd español? La información en esta publicación se puede traducir para ustéd. Para solicitar los servicios de traducción por favor llame al (503) 731-4128.

 
Page updated: February 04, 2007

Click here to go to the Oregon Dept. of Veterans' Affairs outreach contact form

Get Adobe Acrobat ReaderAdobe Reader is required to view PDF files. Click the "Get Adobe Reader" image to get a free download of the reader from Adobe.