OR 213 (SE 82nd Avenue) at SE Duke Street
Sm Circle Fly'g T.tif
OR 213 (SE 82nd Avenue) at SE Duke Street
Safety Improvement Project


The Oregon Department of Transportation (ODOT) finished building a safety improvement project on Oregon Highway 213 (SE 82nd Avenue) at SE Duke Street in Southeast Portland in July 2016. 

Construction

Update (08/05/16):  The majority of the construction work is finished. In early August the new radar detection system will be operational; until that time the traffic signals and pedestrian crossings will be on an automatic timer. After the radar detection is installed, people waiting to cross the street on foot or in their cars will activate the traffic signal, resulting in shorter waiting times. A new street light will also be installed at the NW corner of the intersection. 

IMG_0590.JPG
The new bus pullout at the intersection of SE 82nd Avenue and SE Duke Street is now open. 

Project overview

ODOT selects safety improvement projects based on crash history and the severity of crashes on ODOT right-of-way. Crash data from the most recent five-year period (2008-2012) indicates that 41 crashes occurred in this area. The predominant crash types were rear-end crashes, turning movements and right angle crashes. One pedestrian crash also was recorded at this intersection.​

Budget and funding

This safety improvement project cost approximately $998,000 to complete. Funding came from both state and federal funds.​ 

This project: 

  • Replaced and upgraded traffic signals with larger signal heads/supports and improved illumination at the intersection of SE 82nd Avenue and SE Duke Street.
  • Installed larger street recognition signs north and south of SE Duke Street on SE 82nd Avenue.
  • Added bus pull-out on the southwest corner of SE Duke Street and SE 82nd Avenue.
  • Improved the sidewalk south of SE Duke Street on the west side SE 82nd Avenue between SE Duke Street and SE Claybourne Street.
  • Upgraded ADA Ramps at all four corners of the intersection of SE 82nd Avenue and SE Duke Street.

Click on the links below to view the Project maps:

What is the schedule?

  • Fall​ 2013 - Preliminary design phase
  • Spring 2014 - Public open house

The April 24, 2014 open house included the following materials:

Handouts:

Display Boards:

  • Spring 2015 - Project design completed
  • Summer 2015 - Construction contract awarded
  • November 2015 - Construction starts
  • July/August 2016 - Construction finished (construction was mostly completed by mid-July, only minor work will take place in early August)

How can I get more information?

If you have questions or comments about this project please contact Brandy Steffen, ODOT Community Affairs Coordinator during regular business hours at 503-731-8230 or Brandy.Steffen@odot.state.or.us


For ADA (Americans with Disabilities Act) or Civil Rights Title VI accommodations, translation/interpretation services, or more information call 503-731-4128, TTY (800) 735-2900 or Oregon Relay Service 7-1-1.​​

Podemos proporcionar la información de esta publicación en español. Para recibir información por favor llame al 503-731-4128.

Мы можем предоставить информацию в этой публикации на русском языке. Для получения информации звоните по тел 503-731-4128.​

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128. 
如果您想瞭解這個項目翻譯成繁體中文的相關資訊,請致電  503-731-4128
如果您想了解这个项目翻译成简体中文的相关信息,请致电  503-731-4128.

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화503-731-4128.​

​​​​​​​​​​​
​​​