Oregon Highway 224 (Clackamas Highway)


May 23 - 30, 2015*


*Schedules are subject to change due to weather and site conditions.

There will be no work on Memorial Day, Monday, May 25.​


Oregon Highway 224 at Southeast 135th Avenue

Project Description: The project will improve safety at the intersection of Oregon Highway 224 and Southeast 135th Avenue by replacing the traffic light poles, adding left turn signals for vehicles traveling from Southeast 135th Avenue to OR 224, and adding street lights. The project will also build a new bus pullout east of the intersection, a new sidewalk along the south side of OR 224, after removing the hedge next to the soundwall, and sidewalk ramps on the corners.

Traffic Impacts: No traffic impacts. This project is complete.

For more information: www.oregon.gov/ODOT/HWY/REGION1/Pages/OR224atSE135.aspx​

Oregon Highway 212/224 – Sunrise JTA Project

Project Description: The Sunrise JTA (Oregon Jobs and Transportation Act) Project will address existing congestion and safety problems in the Oregon Highway 212/224 corridor by constructing a new road from Interstate 205 to Southeast 122nd Avenue.

Major project elements include:

    • Constructing a new two-lane limited access highway (one lane each direction) from OR 224 (Milwaukie Expressway) at I-205 to Southeast 122nd Avenue at OR 212/224.
    • Constructing a new I-205 overcrossing that will connect 82nd Drive and 82nd Avenue.
    • Improving bicycle and pedestrian accommodations in the project area.
    • Improving the intersection of Southeast 122nd Avenue and OR 212/224. 
​​Traffic Impacts: ​Travelers should be aware of changes to travel lanes during construction.

​​​​Interstate 205
    •  The left lane at the I-205 northbound off-ramp (exit 13) to OR 224 (Milwaukie Expressway) will be continuously closed for up to 18 weeks during construction of a retaining wall.  On Tuesday, Wednesday and Thursday this ramp will be closed at night for paving from 10 p.m. to 6 a.m.  Motorists bound for OR 224 will continue north to Southeast Sunnybrook Boulevard (exit 14), turn left to proceed to Southeast 82nd Avenue, then turn left on Southeast 82nd Avenue; returning motorists to OR 224 via the southbound exit ramp.
​​Southeast 82nd Drive​
    • At Southeast 82nd Drive, near the intersection of Southeast Lawnfield Road, the travel lanes may be shifted or travelers may be stopped periodically for construction crews to build the new Southeast 82nd Avenue overcrossing connection I-205.
​​​Southeast Mather Road, Southeast Minuteman Way and Southeast Lawnfield Road​
    • At Southeast Mather Road and Southeast Bordeaux Lane expect lane closures, with flaggers directing traffic, Monday through Saturday from 7 a.m. to 5 p.m. for installation of a new water line and water quality treatment pond. 
    • At Southwest Minuteman Way expect one way traffic controlled by flaggers Tuesday through Saturday from 7 a.m. to 5 p.m. for installation of striping and utility adjustments. 
    • Southeast Lawnfield Road is permanently closed (between the Union Pacific Railroad crossing and Southeast 82nd Drive). A new extension of Southeast Minuteman Way connects Southeast Mather Road and Southeast Lawnfield Road.