| OR 224 Preservation Project |
|
|
 |
|
|

|
|
|
A contractor for the Oregon Department of Transportation has completed work on a project to pave Oregon 224 (Milwaukie Expressway) from SE 17th Avenue to the Interstate 205 interchange. Work on the 4.4-mile section of OR 224 began in spring 2006. The contractor finished work on all items in the contract in July 2007.
This $5.9 million preservation project included the following upgrades:
- Paving and striping all lanes of OR 224
- Replacing median barrier, guardrail and various bridge joints
- Upgrading traffic and pedestrian signals
- Adding new sidewalk from SE Harrison Street to Oak Street and additions or improvements to curb ramps throughout the project corridor.
- Two new water quality swales
For project information, contact Judy Shioshi at 503-731-8237
|
|
|
|