Text Size:   A+ A- A   •   Text Only
Find     

Highway 99E Paving
Latest News
Paving began July 5 and will continue until late August.

 

The contractor will flag traffic around-the-clock from 7 p.m., Friday, July 13 to 6 a.m. Monday, July 16 along OR 99E across the Parrott Creek Bridge south of South End Road.

Flagging is needed to replace the membrane the OR 99E viaducts crossing over Parrott Creek (the membrane on the viaducts is a protective layer between the asphalt driving surface and the bridge viaduct structure. The membrane protects the structure from corrosion due to water.) 
 

 

 
Project Elements
OR 99E Improvements
In the summer of 2012, contractors for the Oregon Department of Transportation will repave and restripe sections of Oregon Highway 99E between 10th Street in Oregon City and Pine Street in Canby*. In addition, some changes to lane configurations will occur.
 
*The sections south of the Canemah district, from milepost 13.8 to 15.2 and near the Territorial Road intersection with OR 99E will not be repaved as these sections received safety improvements and new pavement less than five years ago.

 
Adding Left-Turn Lanes
99E Striping
Striping changes on OR 99E south of Oregon City
Several crashes and near miss crashes have occurred along Highway 99E, between Oregon City and Canby. ODOT has been working over the past several years to reduce these crashes by adding left-turn lanes along Highway 99E.
 
Currently, left turn movements are made from the fast (left) lane in each direction of the highway. As cars stop waiting to turn, high speed rear end accidents or near misses often occur. Adding a left-turn lane will reduce the potential for crashes by providing a safe place for drivers to pull on and off the highway. However, the addition of the left-turn lane requires removing one or more through travel lanes along Highway 99E.
 
In the summer of 2012, ODOT will add left-turn lanes in the following locations:
  • Highway 99E south of 2nd Street to near MP 13.8
 
 South from the 2nd Street intersection, ODOT will construct a continuous left-turn lane.  When the left-turn lane is constructed, there will be only one southbound travel lane and one northbound travel lane.
 
  • Highway 99E north of South End Road 
 
North of the South End Road intersection, ODOT will extend the left-turn lane approximately 1/3 of a mile. Adding the left turn median requires removing one southbound travel lane, leaving two northbound travel lanes and one southbound travel lane.
 
Adding the left-turn lanes will improve safety along these sections of highway Removing travel lanes to accommodate the left-turn lanes  is not expected to increase congestion or travel times.
 

 
Construction Traffic Impacts
Paving and striping work will require temporary lane closures and flaggers may temporarily block access to driveways and intersections for short periods. ODOT staff will work with property owners to coordinate access to and from their properties. We anticipate the majority of the work will take place during nighttime hours when traffic volumes are lower on Highway 99E, however, daytime lane closures may take place. 
 
 
Paving and striping work will take place at night when traffic volumes are lower on OR 99E. Paving and striping work will take place each night from 7 p.m. to 6 a.m. up to seven days a week. In downtown Oregon City, lane closures will not begin until 9 p.m.
 
The contractor may also close lanes during the day from 8:30 a.m. to 4:30 p.m. Monday through Friday and from 9 a.m. to 6 p.m. on the weekends. Daytime lane closures will occur in short segments and will not span far.
 
Paving is expected to wrap up in August. Work is expected to wrap up by the end of September. However, it is possible the work schedule could shift due to wet weather.
 
During the work, the contractor will close lanes. Although the road will remain open, drivers should expect delays.
 
Weekend Intersection Closures on Oregon Highway 99E in Downtown Oregon City
 
The contractor closed lanes and intersections along OR 99E between 10th Street and Main Street around-the-clock the weekend of July 9. The closures were needed to replace the membrane on two OR 99E viaducts in Oregon City (the membrane on the viaducts is a protective layer between the asphalt driving surface and the bridge viaduct structure. The membrane protects the structure from corrosion due to water). The contractor closed one lane in each direction and the intersecting streets around-the-clock for one weekend this summer.  
 
The contractor anticipated needing two weekends for this work and finished in one weekend instead. This is good news for weekend travelers along OR 99E in Oregon City. 
 
Traffic Signals will Run a Little Slow
When we pave, we have to remove the traffic signal loop. This loop senses the cars on the roadway and adjusts the signal timing accordingly. When the loop is removed, we will time the signal manually. This means for drivers, they may sit at a red light a little longer than normal. Our ODOT crews will monitor the signal timing and make adjustments as needed. After the final striping is installed the traffic loops will be re-installed and the traffic signals will function normally again.
 
 
Nighttime Noise and Contact Information

 
 

Your home or business may be near enough to the project for the nighttime work to be audible. Paving will take place in a moving operation, so the noise source will move throughout the area during the work.

 

To report noise problems associated with the nighttime paving work or incidents requiring immediate attention during nighttime hours only please call, 503-412-2356.

 

 

 

 

For more information, please contact Kimberly Dinwiddie, ODOT Community Affairs, 503-731-8281 or Kimberly.Dinwiddie@odot.state.or.us