Text Size:   A+ A- A   •   Text Only
Find     
Site Image

TV Highway Paving and Utility Project: Minter Bridge Road to 331st Avenue (Hillsboro)

 

 


 

 

Project Summary

In June 2013, an ODOT and City of Hillsboro paving and utility project began on TV Highway between Minter Bridge Road and 331st Avenue.  Work will continue for over two years with traffic impacts on TV Highway days and nights.

View a project fact sheet, updated May 2014.

View a map of the project in the downtown Hillsboro section area and the associated work

Latest News

Read the weekly construction news for traffic impact information, updated every Friday.

Sept. 29, 2014 update:

Work on Baseline Street:
 
** The contractor is continuing reconstructing and repaving all three lanes of Baseline Street from 10th Avenue to 1st Avenue.  The two exceptions are the blocks from 10th Avenue to 9th Avenue (reconstructing/paving left lane only) and from 7th Avenue to 5th Avenue (reconstructing/paving right lane only).  Work is taking place day and night, Monday through Saturday, with two lanes in a 2-block section closed on Baseline Street 24/7.  Each 2-block section will take approximately 1 week to complete, including paving
 
** The contractor is in the final week this year of 24/7 double lane closures on Baseline Street
 
** Beginning Monday, Sept. 29, and continuing until Saturday morning, Oct. 4, the left and center lanes on Baseline Street between 2nd Avenue and 1st Avenue will be closed 24/7. Paving of this section is scheduled for Friday night, Oct. 3 (weather permitting). 
 
** Also during the week of Sept. 29, the signals on Baseline Street at both 2nd Avenue and 1st Avenue will be disabled and flaggers will be controlling all directions of travel in those intersections.  Additionally, nighttime closures of 1st Avenue at Baseline Street in both directions are planned Tuesday night Sept. 30 or Wednesday night, Oct. 1 AND Friday night, Oct 3.  These closures will begin at 8 p.m. and continue until 5 a.m. the following morning.  A signed detour will be in place directing road users around the closures.
 
** Driveways into and out of businesses and residences on Baseline Street will typically have access during the lane closures. There will be short closures of driveways when the contractor is actively working in front of the driveway. The contractor will be placing “business open” signs at the driveway entrances so customers know to still patronize businesses. Please let us know if you have any questions or concerns/trouble with accessing your business or residence during this work.
 
** Access to the main entrance and emergency room of Tuality Hospital will remain open at all times.  If a detour is necessary to the emergency room, the new route will be clearly marked
 
** TriMet service on Baseline Street will be intermittently affected during this reconstruction work. Temporary bus stop closures will be communicated on www.trimet.org and at the bus stops
 
Work on Oak Street:
 
The contractor completed grinding and paving the left and center lane of Oak Street from Dennis Avenue to 10th Avenue the week of Sept. 23. 
 
** The week of Sept 29, there will be intermittent lane closures on Oak Street between Dennis Avenue and 10th Avenue as driveways are reconnected to the new pavement.
 
Crews have been added over this summer and a significant amount of work will be complete by October 2014.  Please plan for congestion, delays and uneven road surfaces over the next couple of months.  After October 2014, the contractor plans to take a winter break and return in spring 2015 to complete the remaining work by the end of 2015.
 
The contractor and ODOT are working hard to minimize disruption as much as possible, but many impacts are unavoidable. There is increased traffic enforcement in the area.  Please drive cautiously and follow construction signage.
 

To be added to the project email list, email Lili.D.Boicourt@odot.state.or.us

en español
¿Habla español? Esta es información importante sobre una próxima construcción en TV Highway. Para ver una versión en español de este boletín informativo, por favor haga clic aquí.​​
 

 

Project Information
 
ODOT, in partnership with the City of Hillsboro, began construction in June 2013 on a $14 million paving and utility project on TV Highway (OR 8) from Minter Bridge Road to SW 331st Avenue. This stretch includes 10th Avenue, Baseline Street and Oak Street through downtown Hillsboro. Work includes:

•Grinding, reconstructing, paving and restriping TV Highway from Minter Bridge Road to SW 331st Avenue [paving from Minter Bridge Road to Maple Street and from Dennis Avenue to 331st Avenue was complete in 2013]

•Significantly upgrading the City’s water and stormwater systems. Portions of the City’s water and storm pipes will be entirely replaced in downtown Hillsboro [water work is complete as of June 2014; the majority of the stormwater replacement is complete with the remaining amount completed in 2015]

•Improving more than 100 ADA ramps (accessible curb ramps), primarily in downtown Hillsboro

•Repairing and paving the Dairy Creek Bridge (complete)


•Improving signage
 
TV Highway in this section is in poor condition and in need of repair and reconstruction.  In addition, the City of Hillsboro is including major utility upgrades on TV Highway as part of the project. The City’s water mains buried under Oak Street and Baseline Street are at least 60 years old and predominately steel pipe.  The joints between the steel pipes are aging and causing leaks.  Approximately two miles of new waterlines will be installed on this project as part of the annual pipeline replacement program.  The new mains and meters will ensure quality water service to hundreds of commercial, industrial and residential customers along TV Highway.
 
By making all the improvements in one cohesive project, ODOT and the City of Hillsboro will save tax dollars and increase efficiency.
 
View a map of the project in the downtown Hillsboro section area and the associated work.
 
Traffic Impacts and Schedule

Road users on TV Highway will encounter significant construction during the day and night from June 2013 to fall 2015. There will be delays and detours in place throughout construction, especially in downtown Hillsboro. Read the weekly construction news for the latest traffic impacts, updated every Friday.  The following traffic impacts are planned:

  • Lane closures may occur on TV Highway during the day or night, 7 days a week
  • There will be intermittent intersection closures along Oak and Baseline streets
  •  
  • There will be unavoidable temporary business and resident driveway closures, which will be communicated individually to businesses and residents during construction
  • Access to the main entrance and emergency room of Tuality Hospital will remain open at all times. There may be short detours, but temporary signage will direct motorists to the hospital.
  • TriMet service on TV Highway will be intermittently affected during lane and intersection closures. Any TriMet detours will be communicated on www.trimet.org and at the bus stops.
  • There will be intermittent on-street parking restrictions on Oak Street and Walnut Street throughout construction
  • During double-lane and intersection closures, large trucks will be detoured from Baseline Street to Walnut Street. On-street parking on Walnut Street may be limited in some sections to allow for wider trucks. To minimize truck noise on Walnut Street, flaggers will be used to move trucks through intersections without stopping. 
 
This will be a disruptive project on TV Highway. Considerable effort is being made to maintain business and resident access and minimize traffic impacts. Thank you in advance for your patience and please travel slowly and carefully through the construction.
 
Nighttime Noise
Due to high traffic volumes on TV Highway, most of the lane closures and construction activity will occur at night.  The contractor will be required to turn off truck backup alarms during nighttime work after 10 p.m.  Flaggers will be used to move trucks through sensitive intersections without stopping, which will help reduce noise. A 24-hour noise hotline is available to be called at all hours should a noise concern arise. That number is 503-412-2356.  ODOT staff will be available to answer immediate noise concerns during nighttime work by calling the noise hotline.
 
 
Stay Current with the Project
 
*Continue visiting this website. The project website will have current information, including detailed traffic impacts in a weekly construction update posted every Friday.
 
* Visit www.tripcheck.com or call 511 for current traffic conditions and impacts
 
* Call the noise hotline (24-hour number to be called for noise concerns): 503-412-2356.
 
* For more information, to be added to the project email list, or to request a meeting, please contact:
Lili Boicourt, ODOT Community Affairs
PH: 503-731-8247; Email: Lili.D.Boicourt@odot.state.or.us
 

TV Highway Paving Project: 331st Avenue to Quince Street

Construction finished in May 2013 on a project to grind and pave OR 8 (Baseline Street and Pacific Avenue) from 331st Avenue (just west of Hillsboro) to Quince Street (OR 47) in Forest Grove. This included the Baseline/Adair couplet in Cornelius. The eastern half of the Cornelius couplet was not paved because it was recently paved as part of a City project. In addition to grinding, paving and restriping the road, the contractor:
  • Repaired pavement
  • Upgraded sidewalk curb ramps to Americans with Disability Act (ADA) standards
  • Made improvements to the east side of the OR 8/Quince Street (OR 47) intersection including:
    • Striping a crosswalk across OR 8 at Quince Street/OR 47 on the east side of the interchange
    • Adding a pedestrian signal for the new crosswalk
    • Adding a raised pedestrian island at the south end of the new crosswalk
​​