Text Size:   A+ A- A   •   Text Only
Find     
Site Image

TV Highway Paving and Utility Project: Minter Bridge Road to 331st Avenue (Hillsboro)

 

 


 

 

Project Summary

In June 2013, an ODOT and City of Hillsboro paving and utility project began on TV Highway between Minter Bridge Road and 331st Avenue.  Work will continue for over two years with traffic impacts on TV Highway days and nights.

View a project fact sheet, updated August 2013.

View a map of the project in the downtown Hillsboro section area and the associated work.

 

Latest News

Read the weekly construction news for traffic impact information, updated every Friday.

March 17, 2014 update:

Work is continuing on Oak Street between Dennis Avenue and 1st Avenue and on Baseline Street between 10th Avenue and 7th Avenue.  Details are below.

Oak Street
Work is continuing on Oak Street between Dennis Avenue and 1st Avenue.  The right lane of Oak Street in this section is now open. The left lane is currently closed for storm sewer pipe replacement. Work will take place at night and during the day. Traffic impacts include:

** The left lane of Oak Street from Dennis Avenue to 1st Avenue is currently closed 24 hours a day until approximately May 2014.  This includes times when the contractor is not actively working on the project

** At night, the middle lane of Oak Street may also be closed to create a wider work area.  The middle lane will reopen every morning.  Cross streets in this section may also be impacted during the work.

** There will be intermittent sidewalk closures on Oak Street.  When that occurs, sidewalk detour signs will be in place directing pedestrians to the sidewalk on the other side of the street

** Driveways into and out of businesses and residences on Oak Street between Dennis Avenue and 1st Avenue will be available at all times.  There may be very short delays getting into/out of driveways if the contractor is actively working in front of the driveway.  Please stay in touch and let us know if you have any questions or concerns/trouble with accessing your business or residence during this work.  The contractor is obligated to provide access at all times

After the section of Oak Street is complete between Dennis Avenue and 1st Avenue in May (approximately), the contractor will then begin work on Oak Street between 1st Avenue and 4th Avenue.  This will also include a single lane closure in this section 24 hours a day with nighttime and daytime work.

Baseline Street
In early Feb. 2014, work began on storm sewer pipe replacement, sidewalk and ADA ramp work on Baseline Street between 10th Avenue and 7th Avenue.  Work will take place at night and during the day. Traffic impacts include:

** Nighttime lane closures on Baseline Street in this section initially and then a single lane closure 24 hours a day, alternating between the right lane and left lane of Baseline Street. 

** Cross streets in this section may also be impacted during the work

** Driveways into and out of businesses and residences on Baseline Street between 10th Avenue and 7th Avenue will be available at all times.  There may be very short delays getting into/out of driveways if the contractor is actively working in front of the driveway.  Please stay in touch and let us know if you have any questions or concerns/trouble with accessing your business or residence during this work.  The contractor is obligated to provide access at all times

** Access to the Tuality Hospital emergency room will be available at all times

After the section of Baseline Street is complete between 10th Avenue and 7th Avenue in April 2014 (approximately), the contractor will then begin work on Baseline Street between 7th Avenue and 4th Avenue.  This will also include a single lane closure in this section 24 hours a day with nighttime and daytime work

Other work in project
Work is wrapping on Baseline and Oak streets between 10th Avenue and Dennis Avenue testing and chlorinating the new water lines.  There will be daytime single lane closures and nighttime double lanes closures intermittently through this section.  The water line work should be complete in March 2014.

Construction will continue through 2015, with daytime and nighttime lane closures up to 7 days a week as crews move through the project. On TV Highway and some side streets, road users should plan for congestion, delays and uneven road surfaces. The contractor and ODOT are working hard to minimize disruption as much as possible, but many impacts are unavoidable. There is increased traffic enforcement in the area.  Please drive cautiously and follow construction signage.
 

 To be added to the project email list, email Lili.D.Boicourt@odot.state.or.us

en español
¿Habla español? Esta es información importante sobre una próxima construcción en TV Highway. Para ver una versión en español de este boletín informativo, por favor haga clic aquí.​​
 

 

Project Information
 
ODOT, in partnership with the City of Hillsboro, began construction in June 2013 on a $14 million paving and utility project on TV Highway (OR 8) from Minter Bridge Road to SW 331st Avenue. This stretch includes 10th Avenue, Baseline Street and Oak Street through downtown Hillsboro. Work includes:

•Grinding, reconstructing, paving and restriping TV Highway from Minter Bridge Road to SW 331st Avenue

•Significantly upgrading the City’s water and stormwater systems. Portions of the City’s water and storm pipes will be entirely replaced in downtown Hillsboro

•Improving more than 100 ADA ramps (accessible curb ramps), primarily in downtown Hillsboro

•Repairing and paving the Dairy Creek Bridge


•Improving signage
 
TV Highway in this section is in poor condition and in need of repair and reconstruction.  In addition, the City of Hillsboro is including major utility upgrades on TV Highway as part of the project. The City’s water mains buried under Oak Street and Baseline Street are at least 60 years old and predominately steel pipe.  The joints between the steel pipes are aging and causing leaks.  Approximately two miles of new waterlines will be installed on this project as part of the annual pipeline replacement program.  The new mains and meters will ensure quality water service to hundreds of commercial, industrial and residential customers along TV Highway.
 
By making all the improvements in one cohesive project, ODOT and the City of Hillsboro will save tax dollars and increase efficiency.
 
View a map of the project in the downtown Hillsboro section area and the associated work.
 
Traffic Impacts and Schedule

Road users on TV Highway will encounter significant construction during the day and night from June 2013 to fall 2015. There will be delays and detours in place throughout construction, especially in downtown Hillsboro. Read the weekly construction news for the latest traffic impacts, updated every Friday.  The following traffic impacts are planned:

  • Single-lane closures may occur on TV Highway during the day or night, 7 days a week
  • Double-lane closures may occur on Oak and Baseline streets between 10th Avenue and Dennis Avenue from 7 p.m. to 6 a.m. weekdays, until 9 a.m. Saturdays and until 10 a.m. Sundays.
  • There will be intersection closures along Oak and Baseline streets, during a limited number of weekends (approximately 15 total).
  •  
  • There will be unavoidable temporary business and resident driveway closures, which will be communicated individually to businesses and residents during construction
  • Access to the main entrance and emergency room of Tuality Hospital will remain open at all times. There may be short detours, but temporary signage will direct motorists to the hospital.
  • TriMet service on TV Highway will be intermittently affected during lane and intersection closures. Any TriMet detours will be communicated on www.trimet.org and at the bus stops.
  • There will be intermittent on-street parking restrictions on Oak Street and Walnut Street throughout construction
  • During double-lane and intersection closures, large trucks will be detoured from Baseline Street to Walnut Street. On-street parking on Walnut Street may be limited in some sections to allow for wider trucks. To minimize truck noise on Walnut Street, flaggers will be used to move trucks through intersections without stopping. 
 
This will be a disruptive project on TV Highway. Considerable effort is being made to maintain business and resident access and minimize traffic impacts. Thank you in advance for your patience and please travel slowly and carefully through the construction.
 
Nighttime Noise
Due to high traffic volumes on TV Highway, most of the lane closures and construction activity will occur at night.  The contractor will be required to turn off truck backup alarms during nighttime work after 10 p.m.  Flaggers will be used to move trucks through sensitive intersections without stopping, which will help reduce noise. A 24-hour noise hotline is available to be called at all hours should a noise concern arise. That number is 503-412-2356.  ODOT staff will be available to answer immediate noise concerns during nighttime work by calling the noise hotline.
 
 
Stay Current with the Project
 
*Continue visiting this website. The project website will have current information, including detailed traffic impacts in a weekly construction update posted every Friday.
 
* Visit www.tripcheck.com or call 511 for current traffic conditions and impacts
 
* Call the noise hotline (24-hour number to be called for noise concerns): 503-412-2356.
 
* For more information, to be added to the project email list, or to request a meeting, please contact:
Lili Boicourt, ODOT Community Affairs
PH: 503-731-8247; Email: Lili.D.Boicourt@odot.state.or.us
 

TV Highway Paving Project: 331st Avenue to Quince Street

Construction finished in May 2013 on a project to grind and pave OR 8 (Baseline Street and Pacific Avenue) from 331st Avenue (just west of Hillsboro) to Quince Street (OR 47) in Forest Grove. This included the Baseline/Adair couplet in Cornelius. The eastern half of the Cornelius couplet was not paved because it was recently paved as part of a City project. In addition to grinding, paving and restriping the road, the contractor:
  • Repaired pavement
  • Upgraded sidewalk curb ramps to Americans with Disability Act (ADA) standards
  • Made improvements to the east side of the OR 8/Quince Street (OR 47) intersection including:
    • Striping a crosswalk across OR 8 at Quince Street/OR 47 on the east side of the interchange
    • Adding a pedestrian signal for the new crosswalk
    • Adding a raised pedestrian island at the south end of the new crosswalk