Marion, Polk & Yamhill Counties
November 25, 2009
For More Information: Shane Ottosen, Project Manager
ODOT Region 2
(503) 986-2900
Adam Torgerson, Public Information Officer
(503) 986-2880
 
 
 State highway construction 
Nov. 30 - Dec. 5, 2009 
 
Interstate 5 (Pacific Highway, mile post 251.21 to 252.08) 
This project includes grading, drainage, structure, paving, signing, illumination, signals and roadside development work, including a new bridge over Fairview Industrial Drive to provide a northbound on-ramp to I-5 from westbound Kuebler Boulevard.  
 
Most of the project is located on the east side of I-5, just north of the Kuebler Interchange. Impacts to northbound I-5 traffic should be minimal, with occasional night-time lane closures to build portions of the new ramp.  
 
Graphic:
http://farm4.static.flickr.com/3625/3447871698_e1a6a510a3_o.jpg  
 
I-5: Tongue & Groove Barrier Replacement
(Pacific Highway, mile post 244.43 to 249.43) 
This project consists of replacing concrete barrier just south of Salem between mile posts 244 and 249 on I-5. The scheduled work includes concrete barrier installation along the I-5 on-ramps and off-ramps at the Delaney Road interchange.  
 
Some work will occur along the shoulder during the day. Expect nightly lane closures and drive with caution. The project is scheduled to be completed in summer 2010.   
 
This project is funded by the American Reinvestment and Recovery Act. 
 
OR 99E: Signal Improvements
Oregon 99E (Pacific Highway East, Hubbard) 
This project includes construction of a new traffic signal along with other improvements to Oregon 99E’s intersection with D Street in Hubbard. Signal and intersection improvements in Junction City and Glenwood are also part of this project.    
 
Intermittent, temporary lane closures may occur weeknights between 8 p.m. and 6 a.m.   
 
OR 99E: Aurora to Salem Paving
Oregon 99E (Pacific Highway East, mile post 27.09 to 45.82) 
This project includes pavement repair, overlay and markings over an 18 mile section from Aurora (2nd St.) to Salem (Hayesville Dr NE). Paving is scheduled for 6 p.m. to 6 a.m. on Monday evening through Friday morning, with one-lane traffic controlled by flaggers. Motorists should use caution when approaching this location and should expect intermittent, temporary delays.  
 
Paving will continue if weather permits. Additional paving is scheduled for May 2010 for the northern end of the project.  
 
Oregon 99W (Pacific Highway West, mile post 25.83) 
This project includes the construction of a new traffic signal system, addition of a left turn lane on 5th Street (west of Oregon 99W), reconstruction of 5th Street (east of Oregon 99W) as well as construction of curbs, sidewalks and storm sewer improvements.  
 
Intermittent, temporary lane closures are possible weeknights from 10 p.m. until 4 a.m.  
 
This project is funded by the American Reinvestment and Recovery Act. 
 
Oregon 22 (Willamina-Salem Highway) 
This is a pavement preservation project on Oregon 22 (Willamina-Salem Highway) from its junction with Oregon 51 (Independence Highway) to the Center and Marion Street Bridges in Salem. This project also includes bridge deck resurfacing just west of the Marion and Center Street Bridges, across from Capitol Manor.
 
OR51: On Monday Nov 30th the contractor will be installing guardrail during the daytime.  Flaggers will be controlling traffic. Delays of 5 minutes can be expected.  
 
OR22: The contractor will be installing guardrail, constructing bridge upgrades and other miscellaneous work. Work hours are from 7pm until 6 am Sunday through Friday. Drivers can expect one lane of traffic in each direction with no delays. Ramps may be closed, watch for message boards for dates. Watch for construction vehicles entering and exiting the work areas.  
 
This project is funded by the American Reinvestment and Recovery Act. 
 
OR 22: Paving from OR 18 to OR 99W
Oregon 22 (Willamina-Salem Highway) 
Contractors are paving Oregon 22 (Willamina-Salem Highway) from its junction with Oregon 18 (Salmon River Highway) to its junction with Oregon 99W (Pacific Highway West).  
 
Crews will work from 6 p.m. until 9 a.m., Monday through Thursday. No work will take place on the roadway from Friday at 2 p.m. until Sunday at 8 p.m, when operations resume for the week. Single lane traffic will be controlled by flaggers and pilot car while work is ongoing.  
 
Paving is complete. Installation of pavement marking may occur during the night-time and morning hours.    
 
This project is funded by the American Reinvestment and Recovery Act. 
 
OR22: Lancaster Dr. Golf Club Rd. Section
Oregon 22 (North Santiam Highway, mile post 1.91 to 11.79) 
This project includes the installation of concrete median barrier from the Lancaster Drive over crossing of Oregon 22 (North Santiam Highway), east to the start of the divided highway. Crews will also install cable barrier within the median area from the end of the concrete barrier east to Golf Club Road.  
 
Motorist should expect eastbound median and shoulder closures during the daytime. Single lane closures are possible Monday through Thursday, from 6 p.m. to 7 a.m.  
 
Oregon 22 (North Santiam Highway, mile post 11.83 to 14.08) 
This project includes the construction of two new eastbound and westbound bridges, improved on and off-ramps, two new travel lanes for westbound traffic, illumination at the interchange, landscape features throughout the project as well as a new signal at the intersection of the eastbound ramps and Cascade Highway.  
 
The Contractor has moved both the eastbound and westbound traffic onto the newly constructed westbound lanes.  The newly constructed westbound OR22 interchange ramps are open to traffic.  
 
The eastbound on-ramp to Oregon 22 from Cascade Highway has been closed to allow construction of the new ramp. Eastbound motorists should follow signs to the detour route, which follows Fern Ridge Road to Oregon 22.   
 
Motorists should expect intermittent daytime lane closures on Cascade Highway between 9 a.m. and 4 p.m. Please drive with caution through the work zone.
 
More information:
www.sublimityinterchange.com
 
 # # ODOT # #  
 
Project information for northwest Oregon:
http://www.odotproject.info 
 
Sign up for Region 2 news releases:
http://www.oregon.gov/ODOT/HWY/REGION2/contact_us.shtml

 

 
Page updated: November 25, 2009