| New Youngs Bay Bridge work will require overnight detour |
|
| 08/10/2009 |
ODOT Region 2 | Aug. 10, 2009 | 08-205-R2 | For Immediate Release
Media: Adam Torgerson, Public Information Officer, (503) 986-2880
Public: Paul Christiansen, Project Manager, (503) 325-4732
New Youngs Bay Bridge work will require overnight detour
ODOT will use three crews to perform multiple maintenance activities, reducing work duration
ASTORIA – ODOT will close the New Youngs Bay Bridge nightly from 9 p.m. until 6 a.m. beginning Sunday, Aug. 30 until the morning of Friday, Sept. 4, to perform several regular bridge maintenance activities.
While the bridge is closed overnight, an electrical crew will work on illumination systems, while the Astoria drawbridge crew performs traffic gate maintenance and the Seaside bridge crew works on the bridge deck joints.
Variable message signs will direct drivers on U.S. 101 (Oregon Coast Highway) to the detour route on U.S. 101B over the Old Youngs Bay and Lewis and Clark Bridges for the duration of the maintenance work.
Detour map:
http://farm4.static.flickr.com/3436/3798219783_591bfdfd9a_o.jpg
# # ODOT # #
Project information for northwest Oregon: http://www.odotproject.info
Sign up for Region 2 news releases: http://www.oregon.gov/ODOT/HWY/REGION2/contact_us.shtml
|
|
|
|
|