Text Size:   A+ A- A   •   Text Only
Find     
Site Image

Benton, Lincoln & Linn Counties
For More Information:  Steve Schultz, Project Manager
(541) 757-4211
ODOT PIO Angela Beers Seydel 541-726-2442
Email:  angela.beers-seydel@odot.state.or.us


 

Linn, Benton and Lincoln Counties

State Highway Construction

 

 
December 5 - December 11, 2016
 
Lincoln County
U.S. 20 PME: UPRR – Eddyville (Phase 4) (U.S. 20 MP 15.78 – MP 31.48)
Project Summary:
  • Construction of landslide mitigation and geotechnical features
  • Over 350,000 cubic yards of earthwork
  • Construction of roadbed, aggregate base and asphalt concrete pavement
  • Installation of drainage, guard rail, striping, and signing
  • Installation of a wildlife crossing culvert under the new roadbed
  • Erosion control
  • Landscaping
  • Re-routing public traffic onto the new alignment
 
Remarks: Highway closures are now complete, with traffic running on the new alignment. Traffic will remain on the current temporary alignment on the west end of the project until late next summer. Over the winter periodic work will continue throughout the project on drainage, planting, erosion control, and miscellaneous cleanup work. If weather permits, work will continue on the excavation, drainage and blasting on the west end of the project. No delays are expected at this time.
Steven Schultz (541) 757-4158
 
U.S. 101@NE East Devils Lake RD (U.S.101 MP111.0 – MP111.6)
Project Summary:
  • Add a left turn lane on U.S. 101 at NE East Devils Lake Rd.
  • Create wider shoulders and improve sight distance in an effort the reduce crashes.
Remarks: All work is now complete except for minor repairs. Minor repair work will be taking place later in the spring. No delays are expected at this time.
Steven Schultz (541) 757-4158
 
U.S. 101: Whale Cove Culvert Replacement (US101 MP 128.832)
Project Summary:
  • Replace two failing culverts across US 101 south of Depoe Bay
  • The contractor will use a trenchless technology install new culverts
Remarks: A 45 MPH speed zone is in effect for the project site. Please use caution in the work zone. The contractor has completed installation of both culverts and is restoring the project site, including seeding and planting. A portion of the Oregon Coast Trail is diverted onto the shoulder of the highway to avoid the work area. Steven Schultz (541) 757-4158
 
Linn County
OR 34 at Seven Mile Lane (OR 34 MP10.5 – 11.1)
Project Summary:
  • Striping and Signal Pole Installation
 Remarks: Expect to see workers in the area and lane closures or shifts. The project is scheduled to be complete in mid-December.
Daineal Malone (541) 967-3919
 
NB and SB I-5 near OR 34 (I-5 MP 216 – 234)
Project Summary:
  • Concrete pothole patching
Remarks: Single lane closures in both directions will occur Sunday through Thursday nights in the area being patched, 9 p.m. until 6 a.m. the following morning. The project is expected to be completed by late December.
Brian Morey (541) 967-2111
    
 
 ## ODOT ##
 
 

 
 

 

 
 
 
 
 
 
 
 
 
 

 

                         
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 

 
 

 
 

 
 

 
 

 
 

 
 
 
 
 
 
 

 
 

 
 

 
 
Share This