Text Size:   A+ A- A   •   Text Only
Find     
Site Image

Benton, Lincoln & Linn Counties
For More Information:  Steve Schultz, Project Manager
(541) 757-4211
ODOT PIO Angela Beers Seydel 541-726-2442
Email:  angela.beers-seydel@odot.state.or.us


 

Linn, Benton and Lincoln Counties

State Highway Construction

 

August 19-26, 2016
 
Lincoln County
US 20 PME: UPRR – Eddyville (Phase 4) (U.S. 20 MP 15.78 – MP 31.48)
Project Summary:
  • Construction of landslide mitigation and geotechnical features
  • Over 350,000 cubic yards of earthwork
  • Construction of roadbed, aggregate base and asphalt concrete pavement
  • Installation of drainage, guard rail, striping, and signing
  • Installation of a wildlife crossing culvert under the new roadbed
  • Erosion control
  • Landscaping
  • Re-routing public traffic onto the new alignment
Remarks: 10-hour full highway closures will continue Sunday through Thursday nights from 7:30 p.m. to 5:30 a.m. Currently no closures scheduled on Friday and Saturday nights. Construction of Phase 4 continues with drainage, blasting and excavation work near the west end of the project at approximately MP 16. Expect increased truck traffic on the existing U.S. 20 due to material hauling and deliveries on both the east and west ends of the project. Night paving work on the interior of the project will continue. Paving work is being done on the new alignment and should not cause any delays to traffic on the existing U.S. 20 alignment until September or early October. Guardrail replacement work continues on the interior of the project. All other work is taking place away from the existing U.S. 20 alignment.
Steven Schultz (541) 757-4158
 
US101@NE East Devils Lake RD (U.S.101 MP111.0 – MP111.6)
Project Summary:
  • Add a left turn lane on U.S. 101 at NE East Devils Lake Rd.
  • Create wider shoulders and improve sight distance in an effort the reduce crashes.
 
Remarks: All work is now complete except for minor repairs, planting, and seeding. No delays anticipated until seeding and planting takes place in September.
 
Linn County
US 20: Sheep Creek Bridge Repair (Phase 2) (U.S. 20 MP 56.46 – MP 56.81)
Project Summary:
  • Repair the bridge that has been damaged by a landslide that has been pushing against it.
  • The highway is closed for approximately eight weeks, starting August 2.
 
Remarks: The highway is closed to all traffic through the end of September. Bridge construction and roadway excavation continue. Closure point is approximately 11 miles west of the US20/OR126 intersection and 26 miles east of Sweet Home. There is no local detour. Use the alternate routes of OR22 or OR126. Watch for flaggers and increased truck traffic in the area. All campgrounds in the area remain open.
Steven Schultz (541) 757-4158
 
OR 34 at Seven Mile Lane (OR 34 MP10.5 – 11.1)
Project Summary:
  • Construct a new signal at the OR 34 and Seven Mile Lane intersection.
Remarks: Expect to see workers in the area. Beginning in September, lane closures should be expected throughout the day Monday through Friday, 9 a.m. to 3 p.m. The project is scheduled to be completed in November.
Daineal Malone (541) 967-3919
 
OR 34 Alsea to Waldport (MP 27 – MP 46)
Project Summary
  • Apply chip seal, fog seal, and sweep 
Remarks: Travelers should expect delays in the area. Work will be done between 9 a.m. and 7 p.m.
Brian Morey, (541) 967-2194
    
 
 
## ODOT ##
 
 

 
 

 

 
 
 
 
 
 
 
 
 
 

 

                         
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 

 
 

 
 

 
 

 
 

 
 

 
 
 
 
 
 
 

 
 

 
 

 
 
Share This