| Paving near Harrisburg could cause delays |
|
| 09/24/2010 |
September 24, 2010 For more information: Rick Little (541) 726-2442
09-249-R2 email at: mailto:richard.little@odot.state.or.us
Paving on OR 99E could cause delays near Harrisburg
HARRISBURG— A contractor working for ODOT will make pavement repairs to OR 99E in Harrisburg next week.
North Santiam Paving will grind old asphalt and replace it with a new road surface beginning Monday, September 27 and continuing until Thursday, September 30.
From 7:30 a.m. until 4 p.m. each day, motorists will experience single lane restrictions with traffic controlled by flaggers and a pilot car. Motorists should expect 10-20 minute delays during the construction periods.
The $170,000 maintenance project is weather dependent. Should the project be cancelled by inclement weather, it will be rescheduled for the next available opportunity.
Know Before You Go
For the latest road conditions, please visit: www.tripcheck.com