Caveman Bridge Rehabilitation
 
Thank you Grants Pass!
We had a great turnout for the Caveman Bridge open house March 15.
We even had some special visitors who are looking forward to the rehabilitation project when it begins later this summer, after this Labor Day.
CavemanBridgeOpenHouseMarch152017.jpg
Moving Ahead with ODOT - Caveman Bridge story
 
Project Video (February 2017)
 
cavemanbridgefinalgraphic.jpg

 
 
Total Projected Cost
$5.3 million
Construction Schedule
Sept. 5, 2017- Feb. 2019
 
Bids: May 11, 2017
The landmark concrete ‘through arch’ Caveman Bridge opened to traffic in 1931. Designed by famed bridge builder Conde McCullough, it’s in need of repair. More than 18,600 vehicles cross the bridge daily and is rated as ‘structurally deficient’.
 
Problem & Scope: There is cracked, broken concrete and exposed rebar, failed joints and delamination of the bridge deck. This project will rehabilitate the nearly 550 foot long structure -  including grinding off the existing asphalt road surface and replace it with a microsilica deck. Add-on street lights from the 1960s or 70s may also be removed. Scope is still being refined by technical representatives.
Construction timing: ODOT Bridge estimates this may be a 14 month project, with total contract time of 17 months.
There will be 12 non-consecutive full night closures off the bridge.Detours will be in place.
Single lane closures at night 7 p.m. - 7 a.m. will occur regularly throughout the project.
Traffic may be held for up to 20 min. during these night time single lane closures.
  • Sun.12 a.m. thru Mon. 7 a.m.
  • Mon. thru Thurs. – 7 p.m.- 7 a.m.
  • Thurs. 12 a.m. thru Friday 7 a.m.
No work, under the north end of bridge – 7:30 am to 9:00 pm May 1 thru Sept. 30, 2018 for Hellgate Jet Boat season
No work during the 2018 Boatnik Celebration, May 24 - 28, 2018
No work during Concerts in the Park - 6:30 – 9 p.m. Tuesdays, June 19 through Aug. 7, 2018
No lane closures during : Back to the 50s Cruise  and Josephine Co. Fair
 
 
Project Timeline
Spring 2015 - Project Development Team narrows scope, design
May 11, 2017 - Project bid
July  2017 - Sept. 2018 - Construction

GPB3.jpg
GPB4.jpg


 

Project Fast Facts               

Location – Oregon 99-Caveman Bridge       
Overall budget - $5.3 million            
Construction/Contract timeline – Sept. 5, 2017- February 2019                        
 

Need More Information     

Gary Leaming
Project Information Specialist
541-774-6388