Rawhide Construction employees Jared Wilkenson and
Ron Stephens work on a pipe crossing, prior to the Oregon 62 Linn Rd.
to Oregon 234 project. Rawhide is an Oregon Emerging Small Business,
which won the bid for this necessary work before the larger road
improvement project begins this summer.
|
Total Projected Cost
- $4 million
Projected
Construction Schedule - Summer 2013
The existing pavement on Oregon 62 between mile point 10.09 (Linn Road) to mile
point 13.69 (Hwy 234) will also be replaced, with a grind-inlay of new asphalt,
along with new striping in the project area.
Safety will be increased by providing a two-way, center
left-turn lane. Mobility and better traffic flow for all users will also
increase with the project. Westbound traffic will be allowed to turn left onto Barton Road.
ODOT
will be coordinating with property owners along the highway to address existing
or future driveway issues
Eagle Point City Council meeting - Dec. 11, 2012 - Project Background (PDF)
Project
Timeline
- 2011
- 2012 Design
project, purchase right of way
- May 2013 Bid
Let
- Summer
2013 Construction
Project Fast Facts
Location -
OR 62 between Linn Rd. to OR 234
Overall budget - $4.7 million
Construction timeline - Summer 2013
Need More Information:
Gary Leaming
Project Information Specialist
Gary.W.Leaming@odot.state.or.us
541-774-6388
Jayne Randleman
Project Leader
Jayne.A.Randleman@odot.state.or.us
541-774-6394