Patterson Bridge Project
Schedule

April 1998
July 2000

October 2000
February 2001
April 2001
July 2001




October 2001




October 2002


October 2003


July 2004
October 2004
January 2005
Rogue River Bridge Conception, Approvals & Design
Scour Report, Pier Stability Analysis, Scour Mapping & Evaluation, Contractor Prequalification
Exploratory Drilling
Advertise & Award Contract
Power & Communications Utilities Relocate
Deck Overlay, North & South Approach Cathodic Protection, Rail replacement & Support Existing Waterline, New Waterline Approach Status, Contractor Design of Pier 2 Foundation Work
Begin Rogue River Bridge Contract-Construction (ending July 2005)

In-Water Pile Driving (through May 2002)
Work Bridge & Enclosure Construction (through July 2003)
Main Spans Waterline (through May 2004)
Main Spans Cathodic Protection (through May (2004)

In-Water Pile Driving (through May 2003)
Pier 2 Work (1st Opp) (through May 2003)

In-Water Pile Removal (through May 2004)
Pier 2 Work (2nd Opp) (through May 2004)
Work Bridge & Enclosure Removal (through July 2005)
Connect Waterline
In-Water Pile Removal
Clean-Up (complete July 2005)

 