Central Oregon Road Construction
UPDATE: Week of March 13th
The Oregon Department of Transportation (ODOT) is continuing to invest in Oregon’s future with roadway improvement projects throughout Oregon’s central region (ODOT Region 4). ODOT is committed to providing safe, efficient transportations systems. The following projects reflect ODOT’s commitment to make improvements as traffic numbers rise and to make the roadways safer and more efficient for drivers:
ALL WORK IS DEPENDENT UPON WEATHER
DESCHUTES COUNTY
OR 126 (McKenzie Highway), MP 111, Redmond
Highland Avenue is one way eastbound and Glacier Avenue is one way westbound. Ninth Street is one way northbound and 11th Street is one way southbound, between Highland and Forest avenues.
Crews are working to install the city of Redmond’s sewer line project along the north side of Highland Avenue.
Sidewalks along the north side of Highland Avenue are closed. Pedestrians should be aware that the sidewalks on the south side of the road will be closed in the next few weeks and they will need to find alternate routes through the area.
Intermittent closes of streets and alleys between Sixth and 12th streets may take place. Local business access will be maintained.
US 20 (Central Oregon Highway), Bend
Greenwood Avenue, between Third and Eighth streets will be stripped on Thursday, March 16, weather depending. Expect delays during the daytime work.
US 97 (The Dalles – California Highway), MP 113.9, north of Terrebonne
On Tuesday, March 14, from 9 a.m. to 3 p.m., traffic will be reduced to one lane to allow for surveying of the roadway at each end of the structure. Flaggers will control the alternating one-way traffic and access to 10th Street. Expect delays of up to nine minutes.
Crews are preparing to pave in late March.
Wimp Way at US 97 in Terrebonne is temporarily closed to through traffic to facilitate replacement of the Burlington Northern Santa Fe (BNSF) Railroad Bridge and to ensure motorist safety during construction at this intersection.
This bridge is located about one mile north of Terrebonne on US 97 at milepost 113.9. During the first phase of construction, crews will construct a new, two-lane bridge with 10-foot shoulders to the west of the existing bridge. Traffic will remain on the existing bridge during construction. Motorists will be routed to the new bridge in fall 2005. Following this traffic switch, crews will remove the existing bridge.
Negus Way, Redmond
Bridge work continues at Negus Way, from North Canal Boulevard to the east side of the railroad tracks. Crews are constructing retaining walls and bridge supports.
Negus Way is closed between North Canal Boulevard and NE 5th St.
Motorists are advised to seek alternate routes around the closure area, including the usage of the newly completed NE 9th Street extension location between Negus Avenue and Hemlock Avenue. Patrons of Xtreme Fitness will use the newly completed NE Second Street bridge to reach the business.
US 97 (The Dalles – California Highway), MP 152-154, at South Century Drive, near Sunriver
Crews will be in the area to perform clearing and grubbing operations. No delays.
A full diamond interchange will be built to improve safety and operations at the existing intersection and to accommodate an increase in projected traffic. The interchange will consist of two-lane bridges for both north- and southbound traffic on US 97. South Century Drive will go under the two bridges, which are separated by a 120-foot vegetative median.
JEFFERSON COUNTY
US 97 (The Dalles – California Highway), MP 92 and US 26 (Warm Springs Highway), MP 116, Madras
Crews are performing cleanup work this week. No delays.
The US 97/US 26 Willow Creek Bridge - Depot Road Project reconfigured and signalized the intersection of US 97 and US 26 near the north city limits of Madras. This project provides safety and enhancement improvements in the City of Madras on US 26 / US 97 from the existing Willow Creek Bridges (MP 92.12) to the intersection of N.E. Plum Street (MP 91.84) and pavement improvements on U.S. 26 between N.E. Plum Street and N.E. Depot Street (MP 116.80).
US 26 (Warm Springs Highway), MP 116.36 – 116.80, West of Madras
Wildish Standard Paving Company is working to replace the existing, three lane Burlington Northern Santa Fe Rail Road Bridge, west of Madras, with a new, wider, three-lane Bridge.
The deck has been poured for the new bridge. Crews are preparing to pave the structure in late March, with a traffic switch to follow. No delays expected.
Construction activities will take place in the area Monday through Friday, 7 a.m. to 5 p.m. with intermittent night and weekend work possible. Motorists can expect delays of less than 15 minutes when traveling through this work zone. This project is expected to be complete in early 2006.
KLAMATH COUNTY
Tingley Lane (Midland Highway), MP 1.34, Klamath Falls
The Tingley Lane Bridge over the Lost River diversion canal is now open to one lane, controlled by stop signs. Yield to oncoming traffic and be aware of loose gravel. The contractor for the Oregon Department of Transportation will replace the current aging, wood structure with a concrete bridge.
The bridge was closed in summer 2004 after damage was discovered in the bridge deck. It was opened later that year, but restricted to one lane, with a stop sign at each end. The new structure will be a two-span concrete slap bridge, 36 feet wide and 125 feet long. It will be able to handle modern-day loads and truck traffic.
OR 66 (Greensprings Highway) MP 43.48-44.08, west of Klamath Falls
Crews are working on the Spencer Bridge over the Klamath River. No delays anticipated.
US 97 (The Dalles-California Highway) MP 241, Spring Creek Hill
This project is in winter shutdown. Equipment may be in the area.
US 97 (The Dalles-California Highway) MP 243.9, Spring Creek Bridge
This project is in winter shutdown. Equipment may be in the area.
US 97 (The Dalles-California Highway) MP 263.1, Barkley Springs Bridge
Clean-up work is being performed in the area. No delays expected.
US 97 (The Dalles-California Highway) MP 265.6, Algoma Bridge
This project is in winter shutdown. Equipment may be in the area.
Algoma Road is still closed.
US 97 (The Dalles – California Highway), MP 274.73, Klamath Falls
Traffic has been switched to the new bridge structure over California Avenue. Crews are performing cleanup work. Intermittent delays possible.
California Avenue is currently closed to through traffic between North 1st Street and Conger Avenue to facilitate construction of the new bridge. Motorists are advised to seek alternate routes around the area.
US 97 (Dalles - California Highway), MP 275.8, Klamath Falls
Crews from Hamilton Construction Company are working to replace the US 97 Bridge over Greensprings Drive. One lane of traffic is opened in each direction. No delays expected.
OR 39 (Klamath Falls-Malin Highway) at OR 140 (South Klamath Falls Highway) MP 1.58-2.04, Klamath Falls
Crews will be installing pipe and doing ditch work. Flaggers may control motorists’ movements at times. Minor delays possible.
OR 140 (Lake of the Woods Highway), MP 50.81 to MP 57.06, at Doak Mountain, west of Klamath Falls
Work has been stopped for the winter. No delays expected.
LAKE COUNTY
OR 31 (Fremont Highway) MP 46.6-46.9, one mile west of Silver Lake
Work has started to replace the narrow, wood bridge with a new concrete structure. Crews will be in the area to clear and grub shrubs. Single lane closures are possible during tree-clearing operations. Expect minor delays and flaggers.
OR 140 (Warner Highway) MP 17.39 – 18.50, US 395 (Freemont Highway) MP 128.57 – 142.64
This project is in winter shutdown. No delays.
This modernization project will realign and reconstruct Highway 140 to eliminate four curves, install safety features and replace the Parsnip Creek Bridge (MP 18.2) with a box culvert on the Warner Highway. Along, US 395, contractor crews will add two to three inches of new pavement on the Freemont Highway, north of Lakeview. This paving project will improve the aging highway surface in the area and includes upgrades to guardrail and constructing new mailbox turnouts. The project is anticipated to be finished in summer 2006.
For local and statewide construction information visit www.tripcheck.com or dial 5-1-1.