Text Size:   A+ A- A   •   Text Only
Site Image

  • State Radio Project Status Update


    Wampus[1].pngThe State Radio Project is 80 percent complete with all site improvements and technology installations. As of the end of August, microwave installations are 78 percent complete, site installations are 84 percent complete and trunking equipment installations are 77 percent complete. Crews reached substantial completion on five sites in August.
    Preparations continue for the cutover to the new console system. Individual cutover plans created for each dispatch center cover logistics before, during and after cutover. To ensure a smooth transition, key technical staff will be on call throughout the process. System acceptance testing will begin in September before the console system cutover.
Project Information Project Resources
The Oregon Department of Transportation’s State Radio Project is replacing aging public safety communications systems statewide. Focused on repairs and modernization, the project is upgrading the existing radio systems for ODOT and the Oregon State Police to create an integrated statewide network and to allow for shared efficiencies with other users of the radio system.
Project Goals
Project Site List
Report Archives







State Radio Users
Find information specific to users here.
Visit our pressroom for bulletins and updates. 
Interested in bidding on work for the State Radio Project? 
Review a list of upcoming opportunities at the procurement and contracting page.
Interested in colocation opportunities with the State Radio Project?
Interested in receiving State Radio Project updates?
Register with ODOT's email service and select the State Radio Project to be added to the project's email distribution list.
Click here to subscribe
Click here for a brief "how-to" on subscribing
Additional Information