Biglow Canyon Wind Farm
|
|
|
Article Content |
 |
|
|
Facility: Wind energy facility with an authorized peak generating capacity of up to 450 megawatts. Location: Sherman County Status: The facility is operating. (217 turbines with a peak generating capacity of approximately 450 megawatts).
Certificate Holder: Portland General Electric Company Contact: Ray Hendricks Portland General Electric Company 121 SW Salmon Street 3WTCBR Portland, Oregon 97204 503-464-8519 Department of Energy Staff: Duane Kilsdonk Original site certificate signed: June 30, 2006 Current site certificate: Third Amended Site Certificate (October 31, 2008)
History:
- July 22, 2005: Notice of intent received.
- October 12, 2005: Application received.
- March 20, 2006: Application completed (date of filing).
- May 8, 2006: Department of Energy issued a draft proposed order.
- June 9, 2006: Department of Energy issued a proposed order.
- June 30, 2006: Council approved a site certificate.
- August 22, 2006: Request for transfer received.
- November 3, 2006: Council approved Amendment #1 (transfer of site certificate).
- November 6, 2006: Effective date of First Amended Site Certificate.
- December 22, 2006: Request for Amendment #2 received.
- March 14, 2007: Department issued a proposed order.
- April 1, 2007: Beginning of construction.
- May 10, 2007: Council approved Amendment #2.
- May 25, 2007: Effective date of Second Amended Site Certificate.
- December 21, 2007: Beginning of operation (Phase 1).
- August 11, 2008: Request for Amendment #3 received.
- October 31, 2008: Council approved Amendment #3; effective date.
- August 17, 2009: Beginning of operation (Phase 2).
- August 20, 2010: Beginning of operation (Phase 3).
Documents:
- Final Order, June 2006
- Site Certificate, June 2006
- Final Order on Amendment #3, October 2008
Attachment C (Habitat Mitigation Plan)
- Third Amended Site Certificate, October 2008
- Phase 1 Avian and Bat Monitoring Report (Jan. – Dec. 2008), April 2009
- Phase 1 Avian and Bat Monitoring Report (Jan. – Dec. 2009), April 2010
Addendum (summary of threshold analysis), March 2011
- Phase 2 Avian and Bat Monitoring Report (Sept. 2009 – Sept. 2010), Amended June 2012
- Phase 2 Avian and Bat Monitoring Report (Sept. 2010 – Sept. 2011), April 2012
- Phase 3 Avian and Bat Monitoring Report (Sept. 2010 – Sept. 2011), April 2012
|
|
|
|
|
|
|
|
|
|
|
|
|