Text Size:   A+ A- A   •   Text Only
Find     

Klondike III Wind Project

Facility:
A wind energy facility with 176 wind turbines and a combined peak generating capacity of approximately 300 megawatts.
 
Location: Sherman County
 
Status:
The facility is operating.
 
Certificate Holder:
Klondike Wind Power III, LLC

Contact: Kathi Kazala
Klondike Wind Power III, LLC
c/o Iberdrola Renewables, Inc.
1125 NW Couch St., Suite 700
Portland, OR 97209
503-796-6913 
 
Oregon Department of Energy Staff: Duane Kilsdonk
 
Original site certificate signed: July 12, 2006
 
Current site certificate: Fourth amended site certificate (effective March 30, 2011)
 
History:

  • Feb. 17, 2005: Applicant submitted a request for expedited review.
  • March 28, 2005: ODOE approved expedited review.
  • May 13, 2005: Application received.
  • Feb. 6, 2006: Application completed (date of filing).
  • April 18, 2006: ODOE issued a draft proposed order.
  • May 31, 2006: ODOE issued a proposed order.
  • June 13, 2006: ODOE issued a supplemental proposed order.
  • June 30, 2006: Council approved a site certificate.
  • July 31, 2006: Request for amendment #1 received.
  • Oct. 2, 2006: ODOE issued a proposed order on amendment #1.
  • Oct. 23, 2006: Start of construction. 
  • Nov. 3, 2006: Council approved amendment #1.
  • Nov. 8, 2006: Effective date of first amended site certificate.
  • April 12, 2007: Request for amendment #2 received.
  • June 19, 2007: ODOE issued a proposed order on amendment #2.
  • June 25, 2007: Request for amendment #3 received.
  • July 27, 2007: Council approved amendment #2.
  • Aug. 1, 2007: Effective date of second amended site certificate.
  • Oct. 11, 2007: ODOE issued a proposed order on amendment #3.
  • Oct. 16, 2007: Start of commercial operation (123 Phase 1 turbines). 
  • Nov. 16, 2007: Council approved amendment #3.
  • Nov. 27, 2007: Effective date of third amended site certificate.
  • March 17, 2008: Start of commercial operation of the Mitsubishi 2.4-MW turbine (Phase 1).
  • June 21, 2008: Start of commercial operation of phase 2 (51 turbines).
  • Dec. 6, 2010: Request for amendment #4 received.
  • Feb. 15, 2011: ODOE issued a proposed order on amendent #4.
  • March 25, 2011: Council approved amendment #4.
  • March 25, 2011: Council approved mitigation plan for raptor fatality rate exceedence.
  • March 30, 2011: Effective date of fourth amended site certificate. 
  • August 24, 2012: Council approved an amendment of the Wildlife Monitoring and Mitigation Plan.  
 
Documents: