Leaning Juniper II Wind Power Facility
|
|
|
Article Content |
 |
|
|
Facility: A wind energy facility with a peak generating capacity of approximately 201 megawatts. Location: Gilliam County Status: The facility is operating.
Certificate Holder: Leaning Juniper Wind Power II, LLC
Contact: Sara Parsons Leaning Juniper Wind Power Facility c/o Iberdrola Renewables, Inc. 1125 NW Couch St., Suite 700 Portland, OR 97209 (503) 796-7732 Department of Energy Staff: Andrea Goodwin Original site certificate signed: Sept. 24, 2007 Current site certificate: First Amended Site Certificate, Nov. 24, 2009 History:
- Nov. 30, 2005: Applicant submitted a request for expedited review
- Dec. 15, 2005: ODOE approved expedited review
- Feb. 1, 2006: Preliminary application submitted
- Oct. 4, 2006: Amended preliminary application submitted
- May 15, 2007: Application filed (complete)
- July 18, 2007: ODOE issued a Draft Proposed Order
- August 9, 2007: Public hearing on Draft Proposed Order
- August 21, 2007: ODOE issued a Proposed Order
- Sept. 21, 2007: Council approved a site certificate
- Sept. 24, 2007: Site Certificate became effective
- June 19, 2009: Certificate holder submitted a Request for Amendment #1
- Oct. 15, 2009: ODOE issued a Proposed Order on Amendment #1
- Nov. 20, 2009: Council approved Amendment #1
- Nov. 24, 2009: First Amended Site Certificate became effective
- Feb. 15, 2010: Beginning of construction (LJIIA)
- March 16, 2010: Beginning of construction (LJIIB)
- June 9, 2011: Beginning of operation
- Dec. 28, 2012: Applicant submitted a Request for Amendment #2 and Transfer
- Jan. 11, 2013: ODOE issued a public notice on the Request for Amendment #2 and Transfer
- April 10, 2013: ODOE issued a public notice on the Proposed Order on Amendment #2 and Transfer
Documents:
|
|
|
|
|
|
|
|
|
|
|
|
|