South Mist Pipeline Extension

Facility: South Mist is a 62 mile, 24-inch natural gas pipeline. The pipeline connects the Mist Underground Gas Storage Facility with the interstate pipeline system and accommodates growth in demand for natural gas in the western Portland suburbs.

Status: Operating

Location: Washington, Marion and Clackamas counties. The northern terminus is the Bacona Blowdown Station, located in forestland north of Dairy Creek. It extends south and east to the Williams Pipeline Gate Station northwest of Molalla.

Certificate Holder: NW Natural

Contact Information 

SITE CERTIFICATE HOLDER
OREGON DEPARTMENT OF ENERGY STAFF
Melissa Moore
Duane Kilsdonk
220 NW Second Ave.
395 E. Highland Ave.
Portland, OR 97209
Hermiston, OR 97838
503-220-2436
 
To Receive Updates by E-mail:
·          To receive e-mail notices about this project, please click here.
·          To receive e-mail notices for other projects or general EFSC announcements, please go here.
 
About Oregon’s siting process:
·          For more information about Oregon’s siting process outlined in the table below, please go here.
 
Project Status (Table details will be updated as project progresses)
PROJECT PHASE DETAILS
DATE
Site certificate amendment #4: Authorized additional supporting equipment, eliminated the need for horizontal inclinometers in the Sherman Mill Side Area and added temporary staging and lay-down areas related to the added equipment.
July 27, 2007

 
 
July 27, 2007
Site certificate amendment #3: Allowed temporary access and workspace outside the 200-foot corridor, realigned the pipeline at specific locations and added permanent access easements outside the corridor.
April 23, 2004
 
 
 
April 23, 2004
Site certificate amendment #2: Authorized diversion of up to 2 million gallons of water for hydrostatic testing and construction from an additional site and different discharge location.
Dec. 8, 2003
 
 
Oct. 8, 2003
Dec. 5, 2003
Site certificate amendment #1: Allowed for temporary construction access and lay-down areas; made changes to temporary and permanent easements on land outside the 200 foot corridor, made changes related to topsoil storage and segregation, relaxed the requirement to maintain segregation between the pipeline and underground structures to the federal requirement.
Aug. 28, 2003
 
 
 
 
Aug. 28, 2003
March 13, 2003
March 13, 2003