Stateline Wind Project
|
|
|
Article Content |
 |
|
|
Facility: Wind energy facility Current operating capacity: 222 megawatts Location: Umatilla County Status: The facility is operating. Certificate Holders: FPL Energy Vansycle LLC and FPL Energy Stateline II, Inc. Contact: John Goodwin NextEra Energy Resources, Inc. 700 Universe Boulevard P.O. Box 14000 Juno Beach, FL 33408-0420 561-304-5126 Department of Energy staff: Duane Kilsdonk Original site certificate signed: Sept. 14, 2001 Current site certificate: Fourth amended site certificate (effective May 19, 2009) History:
- April 27, 2000: Request for expedited review submitted.
- Jan. 11, 2001: Application submitted.
- May 11, 2001: Application complete (date of filing).
- July 2, 2001: ODOE issued a draft proposed order.
- Sept. 14, 2001: Council approved a site certificate.
- Sept. 15, 2001: Beginning of construction.
- Dec. 21, 2001: Beginning of operation (Stateline 1).
- Jan. 22, 2002: Request for amendment #1 received.
- April 11, 2002: ODOE issued a proposed order on amendment #1.
- May 17, 2002: Council approved amendment #1.
- July 1, 2002: Request for amendment #2 received.
- Aug. 16, 2002: Beginning of construction (Stateline 2).
- Nov. 15, 2002: Revised request for amendment #2 received.
- Dec. 10, 2002: Beginning of operation (Stateline 2).
- Feb. 11, 2003: Request for addendum received.
- March 25, 2003: ODOE issued a proposed order on Amendment #2.
- June 6, 2003: Council approved amendment #2.
- March 25, 2005: Request for amendment #3 received.
- May 19, 2005: ODOE issued a proposed order on Amendment #3.
- June 20, 2005: Council approved amendment #3.
- Jan. 20, 2006: Council approved revisions to the Oregon Wildlife Monitoring Plan.
- Dec. 26, 2006: Request for amendment #4 received (withdrawn).
- Oct. 24, 2008: Revised request for amendment #4 received.
- Feb. 20, 2009: ODOE issued a proposed order on amendment #4.
- March 27, 2009: Council approved Amendment #4.
- May 19, 2009: Effective date of fourth amended site certificate.
- June 9, 2009: Beginning of construction (Stateline 3).
- Nov. 20, 2009: Council approved an amendment of the Wildlife Monitoring and Mitigation Plan.
- Dec. 16, 2009: Beginning of operation (Stateline 3).
Documents:
- Final Order, September 2001
- Site Certificate, September 2001
- Final Order on Amendment #1, May 2002
- First Amended Site Certificate, May 2002
- Stateline Wind Project Wildlife Monitoring Annual Report, May 2003
- Final Order on Amendment #2, June 2003
- Second Amended Site Certificate, June 2003
- Stateline Wind Project Wildlife Monitoring Report: July 2001-December 2003, December 2004
- Final Order on Amendment #3, June 2005
- Third Amended Site Certificate, June 2005
- Oregon Wildlife Monitoring Plan, January 2006
- Stateline Wind Project Wildlife Monitoring Report for 2006, September 2007
- Final Order on Amendment #4, March 2009
- Fourth Amended Site Certificate, March 2009
- Revised Wildlife Monitoring and Mitigation Plan, November 2009
- Stateline 3 Wildlife Monitoring Report, October 2010
|
|
|
|
|
|
|
|
|
|
|