Text Size:   A+ A- A   •   Text Only
Find     
Site Image

MT-HOOD-HWY[WEB_Header(Png-8)].png

Enter the virtual open house

 

  

Construction Update April 27-May 1, 2015

April 27, 2015

Video of season one work: https://youtu.be/kgfhkhSNNHg


U.S. 26 Mt. Hood Safety Construction Update

April 27-May 1, 2015

During the week K&E Excavating will work Monday through Friday from sunrise to sunset. This week's work will include 24-hour flagging on the west end of the project and blasting on Tuesday, April 28. Hauling will also continue along Lolo Pass Road. Below are details about how construction will affect travelers:

U.S. 26 Mt. Hood Highway

  • 24-hour flagging will occur on the west end of the project at Map Curve from 5 a.m. Monday to 10 a.m. Friday. Delays associated with the flagging should be minimal however; it could last up to 20-minutes. Starting at 10 a.m. Friday and until 5 a.m. Monday, U.S. 26 will have one lane open in each direction. The 24-hour flagging will allow the contractor to work on the steep slope on the north side of U.S. 26 using a barrier of shipping containers to prevent rocks from rolling into U.S. 26. 24-hour flagging will take place Monday through Fridays until May 21.
  • Up to one hour closure of U.S. 26 5:30 p.m. to 6:30 p.m., Tuesday, April 28 for rock blasting. This is subject to change due to site conditions and work progress. An updated email will be sent out if the date changes. ODOT and the Hoodland Fire Department have established communication protocols to ensure people get lifesaving services during the one hour road closures. These communication protocols were in place during the 2014 season.
  • Monday through Friday, travelers will encounter traffic stops controlled by flaggers, and lane and shoulder closures from sunrise to sunset throughout the three mile project area...
  • With the exception of 24-hour flagging, one lane will remain open in each direction for a nearly three mile stretch of U.S. 26 from east of Kiwanis Camp Road to east of the Mirror Lake Curves. This lane closure will remain in place around-the-clock until October 31.

Lolo Pass Road

Hauling will continue along Lolo Pass Road and take place Monday through Friday from sunrise to sunset. People in the area should use caution and expect truck traffic. The tips below can help travelers share the road safely with trucks.

Road 31

Road 31 will close to all traffic around-the-clock Monday through Thursday.

April 20 flagging delays

Travelers through the work zone experienced significant delays the afternoon of April 20 as emergency responders from all across Clackamas County responded to a three alarm fire in Government Camp. To keep lifesaving emergency responders moving, flaggers working on the U.S. 26 Mt. Hood Safety Project stopped all non-emergency traffic for long periods of time throughout the afternoon. This delayed several travelers much longer than anticipated 20-minutes. ODOT and K&E Excavating apologize for the delay; however, emergency service vehicles will always have priority to get through the construction zone when responding to emergencies.

ODOT would also like to thank K&E Excavating for their support to the firefighting efforts through supply of resources and ensuring emergency services could safely and quickly respond to the fire in Government Camp.
 



Construction Update April 20-24, 2015

April 9, 2015

For information: Kimberly Dinwiddie, 503-539-8454, Kimberly.Dinwiddie@odot.state.or.us


U.S. 26 Mt. Hood Safety Construction Update

April 20-24, 2015

During the week K&E Excavating will work Monday through Friday from sunrise to sunset. This week's work will include 24-hour flagging on the west end of the project and blasting on Tuesday, April 21. Due to the winter weather, the blast for Thursday, April 16 is canceled. Hauling will also continue along Lolo Pass Road. Below are details about how construction will affect you:

U.S. 26 Mt. Hood Highway

  • 24-hour flagging will occur on the west end of the project at Map Curve from 5 a.m. Monday to 10 a.m. Friday. Delays associated with the flagging should be minimal however; it could last up to 20-minutes. Starting at 10 a.m. Friday and until 5 a.m. Monday, U.S. 26 will have one lane open in each direction. The 24-hour flagging will allow the contractor to place a shipping container along the north side of U.S. 26 between the work on the steep slopes and traffic on the highway to prevent rocks from rolling into U.S. 26. 24-hour flagging will take place Monday through Fridays until May 21.
  • Up to one hour closure of U.S. 26 5:30 p.m. to 6:30 p.m., Tuesday, April 21 for rock blasting. This is subject to change due to site conditions and work progress. An updated email will be sent out if the date changes. ODOT and the Hoodland Fire Department have established communication protocols to ensure people get lifesaving services during the one hour road closures. These communication protocols were in place during the 2014 season.
  • Monday through Friday, travelers will encounter traffic stops controlled by flaggers, and lane and shoulder closures from sunrise to sunset throughout the three mile project area...
  • With the exception of 24-hour flagging, one lane will remain open in each direction for a nearly three mile stretch of U.S. 26 from east of Kiwanis Camp Road to east of the Mirror Lake Curves. This lane closure will remain in place around-the-clock until October 31.

Lolo Pass Road

Hauling will continue along Lolo Pass Road and take place Monday through Friday from sunrise to sunset. People in the area should use caution and expect truck traffic. The tips below can help travelers share the road safely with trucks.

Road 31

Road 31 will close to all traffic around-the-clock Monday through Thursday.

 

 

Project Elements:

ODOT will construct a project along a nearly eight mile stretch of U.S. 26 between Kiwanis Camp Road and OR 35 to improve safety by reducing severe crossover crashes and rockfall.

·     Paving an eight mile section of U.S. 26 between Silent Rock and OR 35

·     Cutting back the slope along a 600 foot section at Map Curve to provide a 27 foot wide ditch for rocks to land away from the road·

·     Cutting back the rock slope east of the runaway truck ramp to east of the Mirror Lake trailhead·

·     Highway widening to install a median barrier·

·     Placing a concrete barrier along a 1.6 mile section between the east and westbound lanes of U.S. 26 from just east of the run away truck ramp and east of the Mirror Lake curves.

·     Construction of a retaining wall to reduce impacts to existing trails from highway widening work·

·     Extending the westbound passing lanes for a total of about 1,400 feet·

Project Schedule: Work is expected to take place in the months of April-October each year in 2015 and 2016.

 
 
 

Aug. 20, 2014 Lolo Pass Public Meeting Details

Thank you for sharing you concerns and ideas about trucks on Lolo Pass Road and other haul roads. Here is a summary of the concerns from the public and the responses from ODOT. LoloPassRoadMeetingResponses.pdfLoloPassRoadMeetingResponses.pdf
 
Below is the video shown at the Aug. 20 Public Meeting describing the hauling operations for the U.S. 26 Mt. Hood Safety Project.
 
 
 

 U.S. 26 Mt. Hood Safety Projec Hauling Operations

 
 
 Below is a video summary of ODOT's presentation and responses at the Aug. 20, 2014 meeting.
 
 
 

 Aug. 20, 2014 Lolo Pass Road Meeting Snapshot

 

Project Summary

The Oregon Department of Transportation is currently designing a project to improve safety by reducing severe crossover crashes that lead to fatalities and serious injuries and reduce rockfalls on the Mt. Hood Highway (U.S. 26) just east of Rhododendron and Oregon Highway 35.
 
 
Work will include:
 
  • Placing a concrete barrier between the east and westbound lanes of U.S. 26.

  • Cutting back the rock slope from the highway and building retaining walls to protect historic trails

  • Repave nearly eight miles of U.S. 26 from east of Rhododendron to OR 35
 
 

Construction Impacts

   

Construction will take place from April 1 through October 31 in 2014, 2015 and 2016. During construction, you will still be able to get to your favorite spot on the mountain or wherever you are heading. However, the reality is construction will delay people moving through the area. While we will have some short-term highway closures and there will be some delays, we will work to keep people moving.
 
Here is what to expect when construction takes place:
 
  • Travelers should expect closures up-to one hour three days a week Monday through Thursday in the early evening between 5:30 p.m. and 7:30 p.m. for blasting the rock slopes. ODOT is still working the details to the exact time of these closures. Not all of these closures will take a full hour. However, it is best to plan on being delayed for an hour during these times. The closures are times based on how many vehicles are using U.S. 26 and on available sunlight. Nearby trails will also close briefly during the blasting operations.
 
  • Intermittent traffic stops lasting 20-minutes anytime the contractor is actively working
 
  • One lane closed between Kiwanis Camp Road and Mirror Lake around-the-clock for rockfall and retaining wall work. This means only one lane will remain open in each direction.
    (See photo to the right) Mt Hood Safety Project_Temporary Work Zone_Draft 8-23-13 (2).jpg

  • Increased truck traffic on U.S. 26 and on roads leading to disposal sites including Lolo Pass Road, Trillium Lake Road and Laurel Road.
 
  • Intermittent single lane closures and flagging for other work instead of full highway closures.
 
  • Construction work will not occur on holidays and Sundays.
 
  • No construction work will occur from November to March of each year. During this time all three lanes will re-open.

 
 
Increased Truck Traffic
 
Nearly a million cubic yards of rocks and other materials will go to several disposal sites on Mt. Hood. These sites include: ODOT Maintenance yard at U.S. 26 and OR 35 Junction, Tamarack Quarry, Laurel Quarry and two sites along Lolo Pass Road. This means increased traffic on U.S. 26 and the roads leading to these disposal sites.
 
 
ODOT and K&E Excavating are committed to safety. Truck drivers are required to follow all traffic laws and be aware of other people using the road.
 
Trucks are hauling rocks, trees and other materials from the slopes of U.S. 26 to several sites on Mt. Hood. Hauling will occur April through October in 2014 and 2015, starting at sunrise and until 7 p.m. We apologize for the inconvenience.
 
Here are some things you can do to stay safe when sharing the road with trucks:
 
BE VISIBLE: If you are walking, jogging, riding a bike or riding a horse be as visible as possible and wear reflective clothing.
 
LISTEN for oncoming trucks and do not use head phones that could block the sound of trucks approaching.
 
BLIND SPOTS: When riding a bike, ride with traffic and in the middle of the travel lane so you do not end up in a trucks blind spot.
 
WALK FACING TRAFFIC: When walking, walk on the opposite side of the road to keep your eye on oncoming traffic and be more easily seen.
 
PULL OUT SAFELY: When pulling out of your driveway onto the haul roads, fully stop and look for trucks and other road users before proceeding. Consider parking so that you can pull out of your driveway rather than back out to increase your ability to see oncoming trucks.
 

 

 

Crashes and Safety Concerns on U.S. 26

The Mt. Hood Highway is one of the most beautiful drives in Oregon taking travelers through the Mt. Hood National Forest. However, many safety concerns exist along this highway and many crashes have occurred. And sadly, some crashes prove fatal. crashmthood2.JPG
 
 
Crashes between a half-mile east of Kiwanis Camp Road to east of the Mirror Lake Trail Head (mileposts 49.4-52.2) from 2002-2011
 
109 crashes occurred
30 were cross-over crashes of which
11 crashes were head-on
4 people died
88 people were injured
 
 
 
 
 
The purpose of this project is to reduce the crossover crashes that cause severe injury and even death. Placing a concrete barrier in the middle of U.S. 26 can help reduce the most severe of crashes.
 
An independent team of traffic safety, emergency response, and highway professionals performed a Road Safety Audit of U.S. 26 between Camp Creek and Government Camp determined that placing a concrete median as well as reducing rockfalls and extending passing lanes would improve highway safety.
 
To learn more about the safety audit and crashes along U.S. 26 click here.

 

Schedul

  • Construction Began – July 2014
  • Construction Ends* - 2016
  • *subject to change based upon weather and site condition

 

 More Information 

Read ODOT's responses the written comments submitted to ODOT in the spring of 2013 from the virtual and in person open houses.

Written Public Comments from Spring 2013.pdfWritten Public Comments from Spring 2013.pdf

Read the frequently asked questions that we heard in the spring of 2013 and the responses from ODOT.
 
 
Review documents sent from ODOT to FHWA describing inconveniences and temporary closures to the Laurel Hill Chute, Mirror Lake and Pioneer Bridle Trails during construction of the U.S. 26 Mt. Hood Safety Project.
 
Virtual Open House from March 2013 explaining safety concerns and project elements:
 

 

Contact Information

 

For questions or comments about the Mount Hood Highway Safety Project, please contact: 
 
Kimberly Dinwiddie, ODOT Community Affairs

 

(503) 731-8281

 
 
*Official project name as noted in the Statewide Transportation Improvement Plan is FFO-US26: MP 49.2 - MP57.45