The Condon State Airport Taxiway, Taxilane, and Apron Surface Seal Project will begin July 6th, 2026.
This project will include crack seal, pavement patching, surface seal, and new pavement markings on the taxiways, taxilane, and aprons.
Surface Closures and Project Phasing:The taxiways, taxilane, and aprons are expected to be closed for 5 days between 4 work areas.
The work areas are designed to keep closure impacts to a minimum. We will reopen each surface as quickly as possible.
Project Schedule: - Project start - Monday July 6th
- Monday July 6th - the main taxilane (green work area) and Taxiway Bravo (purple work area) will be closed
- Tuesday July 7th - The South Apron (gray work area) will be closed
- Wednesday July 8th through July 10th - The South/Hangar Taxilane and North Apron (blue work area) will be closed
- Thursday July 9th through Friday July 10th - All work areas will be closed
- Project completion - Friday July 10th
For a better look at the work areas, please see the Construction and Safety Phasing Plan linked at the bottom of this notice.
Important Operating Information(!) The runway will remain open throughout this project. Back-taxi on the runway may be required depending on taxiway closures. Access to tie-down parking and hangars may be limited or restricted depending on taxilane and apron closures.
(!!) Please check
NOTAMs for closure times and the most current airport surface closures. Helicopters may arrive or depart directly to/from the east hangar taxilanes.
(!!!) As always, please remain outside of, and avoid low flight over closed work areas.
Thank you for your patience while we maintain the Condon State Airport.