MLRR Grassy Mountain - Permitting Process Overview

Calico Resources USA Corp. - Grassy Mountain

Permitting Process Overview

There are 10 key steps to the permitting process (see sidebar).

Where is the Calico Grassy Mountain project in the process?

To submit a Consolidated Application, the first 4 steps must be completed.


The review and permitting process for the Consolidated Application includes Steps 5-10 as shown in the following flow diagrams. Click here to display a larger flowchart in PDF format (2 pages)

The permitting process provides multiple opportunities for the public and interested stakeholders to participate in reviewing and commenting on Calico's application and the consolidated permit requirements.

The Grassy Mountain project is currently on Step 7 - preparation of an Environmental Evaluation and Socioeconomic Impact Analysis. 



 