OR 213 (Cascade Highway South): I-205 to Conway Drive

Project Summary: This is a project to repave the section of Oregon 213 (Cascade Highway South) from I-205 to Conway Drive in Oregon City.  The work includes roadway repairs, repaving, and required upgrades and improvements to structures, signing and signals.
 
Most of the work will occur at night, with some intermittent day work to minimize construction impacts to the community and motoring public.
Latest Information: Work on the first of the two construction seasons will begin September 2, 2008 and will be suspended by the end of November 2008.  The second season will re-start in late March 2009 with a final completion date scheduled for September 30, 2009.
  
A 24-hour construction hotline has been activated.  Please call 503.412.2345 to report work site concerns. 
 
Read the weekly construction news  that details traffic impacts on the project, updated every Friday.

Project Information
The project was awarded to a construction contractor in August 2008. Construction will begin September 2, and is scheduled to be completed by September 30, 2009.

ODOT Contact Information
ODOT Community Affairs Coordinator:  Elizabeth Craig
• E-mail:  Elizabeth.Craig@odot.state.or.us
• Voice:     503.731.8237
 
ODOT Project Coordinator:  Don Bergmann
• E-mail:   Donald.L.Bergmann@odot.state.or.us
• Voice:     503-731-3060
 
24-hour Construction Hotline:  503.412.2345