U.S. 30 (NW St. Helens Road) Paving Project: NW McNamee Road to milepost 17.93

Current Status

Construction began in May 2013 and will be complete by fall 2013.

Construction Impacts

Motorists can expect:

  • daytime and nighttime lane closures with flaggers directing traffic on U.S. 30 and up to 20-minute delays
  • driveways and cross-streets will be temporarily blocked while the grinding and paving operation moves past them. Motorists will still be able to access these driveways and cross-street by driving past the the paving area, making a u-turn and approach from the other side of the highway
  • work will occur primarily on weekdays
  • no lane closures during morning and afternoon rush hours, during the day on weekends or on holidays
  • in late summer 2013, U.S. 30 will be reduced to one lane in each direction around the clock for four days at Cornelius Pass Road while the contractor applies the waterproof membrane to the bridge over McCarthy Creek. During this same time, Cornelius Pass Road will also be closed to all traffic as part of a separate safety improvement project (more information). This closure will occur between 10 p.m. on a Friday to 4:30 a.m. on the following Wednesday
During construction, you may sign up to receive weekly updates about anticipated traffic impacts by visiting this Web page: www.oregon.gov/ODOT/HWY/REGION1/Pages/WeeklyUpdate.aspx.
 
Construction noise may be audible to residents living in the project area during work hours.
 
Residents with noise complaints during construction may call the 24-hour noise complaint hotline: 503-646-0231.  

 

Project Description

ODOT will repave both direction of U.S. 30 (NW St. Helens Road) between McNamee Road and milepost 17.93, just south of the Columbia County line. Project area map (JPG).

This project also will:

  • restripe the highway to remove the double yellow lines at driveways and provide longer left turn refuge areas
  • flatten the bump in the roadway on eastbound U.S. 30, west of the truck scale
  • apply a waterproof membrane to the bridge over McCarthy Creek, just east of Cornelius Pass Road, to reduce deterioration of the structure
  • repair the shoulders

ODOT is also constructing a safety improvement project on U.S. 30 at Cornelius Pass road in 2013. More information about this project.

 

Other Projects in this Area

 

Project Contact

If you have any questions about this project, please contact:

Jilayne Jordan
ODOT Community Affairs Coordinator
503-731-8237
Jilayne.Jordan@odot.state.or.us