Interstate 84 (Columbia River Highway/Banfield Expressway)


August 29 - September 5, 2015*

*Schedules are subject to change due to weather and site conditions.

Heavy rains Friday, August 29 and Saturday, August 30 could mean construction schedule changes and slick road surfaces in NW Oregon. Read more . . .

No work will take place between Friday, September 4 at noon and Monday, September 7 in observance of the Labor Day holiday.  ​ 

Interstate 84 Troutdale Interchange at Exit 17

Project Description:  The project will widen Marine Drive between the two frontage roads to allow for two-way traffic. It will also replace the existing Interstate 84 overpass bridges at Marine Drive with a new bridge. The Marine Drive intersections at the Frontage Roads will also be improved.

​Traffic Impacts: Motorists should exercise caution in the project workzone, as construction vehicles may be entering and exiting travel lanes.  Travelers should expect periodic nighttime lane and ramp closures on I-84, as well as lane closures along the Frontage Roads and Marine Drive as the contractor performs paving and striping Monday through Friday.​ 

Motorists approaching the interchange on Marine Drive should expect shifted lanes and additional traffic control and signing.  Please be cautious and obey all posted signs and devices.

​For more information: www.i-84TroutdaleExit17.org

Interstate 84 at the Bridge of the Gods 

Project Description:  The Bridge of the Gods between I-84 in Cascade Locks to SR-14 in Washington will be closed for summer events to all vehicle, bicycle and pedestrian travelers.

Traffic Impacts: Travelers should expect full bridge closures on the follow dates and times:
  • Saturday, August 29 from 8:30 to 9:15 a.m. for the Community Bridge Walk
  • Saturday, September 19 from 7:30 to 8:30 a.m. for the Bridge of the Goddesses Run

For more information: www.PortofCascadeLocks.org or call (541) 374-8619

Interstate 84 from Cascade Locks to Hood River

Project Description:  This project will replace 12-miles of center concrete barriers on I-84 from Cascade Locks (milepost 46) to Hood River (milepost 64) between July and November 2015, before paving in summer 2016. The project will result in a smoother ride, increased safety and extend the life of the highway.​

Traffic Impacts: Work will be put on hold until the middle of September.

For more information: www.i84construction.org  

​​​​​​​​​​​​​​​​​​​​