Text Size:   A+ A- A   •   Text Only
Find     
Site Image

Interstate 84

Aug. 23 - Aug. 30, 2014 *

*Schedules are subject to change due to weather and site conditions.
 
  
I-84 Troutdale Interchange at Exit 17
 
Project Description:  The project will widen Marine Drive between the two frontage roads to allow for two-way traffic. It will also replace the existing I-84 overpass bridges at Marine Drive with a new bridge. The Marine Drive intersections at the Frontage Roads will also be improved.
 
Traffic Impacts: Traffic lanes on North Frontage Road are shifted approximately 4 feet to the south as they approach Marine Drive. Drivers should exercise caution as large construction equipment may be operating in the right hand shoulder of this area.  Night time lane closures may occur on freeways and frontage roads as the contractor hauls material around the site.
 
 
 
Interstate 84 at the Sandy River and Jordan Road Bridges
 
Project Description: This project replaces two bridges on I-84 over the Sandy River east of exit 17 in Troutdale, and repairs two bridges over Jordan Road east of the Sandy River at exit 18.
 
Traffic Impacts:  The speed limit is reduced to 50 mph in both directions on I-84 over the Sandy River and over Jordan Road east of the Sandy River. Watch for roadside construction crews. Watch for construction vehicles entering and exiting the travel lanes and ramps.
  
Expect brief delays between 7 a.m. and 4 p.m. while traffic is controlled by flaggers on Jordan Road at I-84. Watch for pedestrians, roadside work crews and construction vehicles entering and exiting the roadway. Please obey parking restrictions.
 
Watch for work crews on bicycle-pedestrian paths. Approach the work areas with caution, stay clear of construction activities and obey instructions from flaggers. Please drive carefully through the work zones.