Text Size:   A+ A- A   •   Text Only
Find     
Site Image

Oregon 99W

Aug. 23 - Aug. 30, 2014 *

*Schedules are subject to change due to weather and site conditions.

 

Oregon Highway 99W (SW Barbur Boulevard) at Newbury and Vermont Bridges
 
Project description: Construction is underway to repair and rehabilitate two bridges on Southwest Barbur Boulevard (OR 99W), just south of Capitol Highway in the Hillsdale area.
 
Traffic Impacts: Expect single lane closures in both northbound and southbound directions of SW Barbur Boulevard between the exit to Capitol Highway (OR 10) and Brier Place Monday through Friday from 6 a.m. to 5 p.m. for bridge deck repair, pipe work and paving on Barbur Boulevard. Expect congestion, especially during peak hours. Use caution. Bikes on Roadway.
 
For more information: www.barburbridges.org
 
Oregon Highway 99W (Pacific Highway), SW 72nd Avenue to Oregon 217
 
Project Description: The required road improvements include widening OR 99W southbound to include a new lane and sidewalk, a landscaped center median and widening the OR 217 northbound off-ramp to S.W. 72nd Avenue. This construction project is being done by a private contractor and is required by the City of Tigard for the development of a WalMart store on Dartmouth Street along OR 99W. A contractor for WalMart will make the required road improvements. Lanes will not close during daytime hours.
 
Traffic Impacts:  Expect alternating overnight lane closures and restrictions in the east and westbound lanes on OR 99W for approximately 1.5 miles from OR 217 and 72nd Avenue for construction activities from 9 p.m. to 5:30 a.m. Monday through Friday.
 
Several activities are occurring on OR99W Monday through Friday. Work activities on OR 99W include sidewalk work, lane, irrigation and landscaping, temporary lane markings, concrete island enhancements and signage and striping work.
 
Bicyclists:  Check this link for detour information:
http://www.tigard-or.gov/community/bike_tigard/default.asp
 
 

 

Oregon Highway 99W (Pacific Highway), Durham Road to Fischer Road

Project Description: Work is underway on a project to improve safety on OR 99W from Durham Road to Fischer Road in King City and Tigard.  Safety improvements include:
 
·    Closing the center median opening on OR 99W at Royal Villa Drive. A left-turn lane and a U-turn signal will be installed at Fischer Road. This will assist southbound travelers who are bound for Royal Villa Drive or wish to head north
·     Building a bus stop pullout on OR 99W southbound just south of Fischer Road
·     Adding new sidewalk on OR 99W northbound from Fischer Road to Tigard Towne Square
·     Lengthening the left turn lane on OR 99W northbound for Fischer Road and for Durham Road
·     Adding new lighting at the intersection of OR 99W and Durham Road
 
Traffic Impacts: Single lane closures may occur on OR 99W and on Durham and Fischer Roads between 9 a.m. and 3 p.m. for traffic signal work Monday through Friday. Please note: Kerr Contractors are also working concurrently within the same work zone for another project.
 
Plan for congestion and short delays on OR 99W, Fischer Road and Durham Road throughout construction.
 
  
Oregon Highway 99W (Pacific Highway) Northbound at I-5 Northbound
 
Project Description: Construction began on a project to improve safety and operations in the area of OR 99W northbound and I-5 northbound, spanning the Tigard/Portland city limits (from approximately SW 67th Avenue to SW 58th Avenue).  Once complete, traffic in the area should see a reduction in crashes and all road users will have a safer environment. Construction is slated for completion in fall 2014.
 
Traffic Impacts: Single lane closures northbound (Tigard to Portland direction) nightly Monday through Friday between 7 p.m. and 6:30 a.m.