| Powell Blvd Pavement Preservation |
|
|
 |
|
|
|
|
|
| Project Summary: |
This project will pave Powell Blvd (U.S. 26) between SE 51st Ave. and I-205. |
| Construction Status and Timeline: |
The project will go to bid in December 2009. Work is expected to begin early 2010. |
| Latest Information (August 2008) |
A project Open House was held in June 2008.
Another Open House will be held before construction begins.
|
|
| Project Summary |
|
The Oregon Department of Transportation (ODOT) is planning a 2.3-mile paving project on Powell Boulevard (U.S. Highway 26) between SE 51st Avenue and SE 50th Avenue. The roadway has deteriorated from high usage and is severely rutted in a number of locations.
As part of the paving project, sidewalk ramps will be brought into ADA compliance and two new pedestrian mid-block crossings will be installed near SE 57th Avenue and SE 75th Avenue.
Proposed Project Improvements
* 127 reconstructed sidewalk ramps
* 48 new sidewalk ramps
* 2 new marked pedestrian crossings between 57th & 58th Avenues and at SE 75th Avenue
* 8 new vegetated stormwater treatment planters
* Over 10,000 tons of new asphalt surfacing
* Extended Left Turn Storage at SE 86th Ave. and Powell Blvd
Construction is expected to begin in early 2010 and be completed by the end of that year.
|
| ODOT Contact Information |
|
Mike Mason, Community Affairs Coordinator, (503) 731-8246