Fern Valley Interchange
FVWebPix.jpg
Southbound on-ramp closure set for up to five days on May 16 through May 20. This work ties in the new permanent with the temporary on ramp.
 
May Phoenix interchange update
Full spring has sprung on the Fern Valley interchange project. Here are a few items we’re working on and timelines. Construction is lining up well to have this project completed by the end of the contract date of September 30.
Northbound off and southbound on-ramps:  with the old overpass removed, work began quickly on grooming the new ramps. The southbound on-ramp is graded, rocked and paved.  Next week, the first of several concrete pours will begin. 
Once that work is complete, and before it is open to traffic, there will be up to a five day closure of the southbound on-ramp beginning Monday, May 16 to allow the contractor to make the final connections. 
Southbound trucks will be detoured to exit 27 (south Medford interchange) and other traffic will be directed to the Talent interchange (exit 21) until that work is complete.
Look for the new southbound on-ramp to open in late May. The northbound off ramp is more complex as there will be a water quality detention pond between it and the northbound lanes of the interstate. That is scheduled to open later in July.
Striping Tempoary striping has been refreshed, and awaiting permanent striping once all the ramps are complete.  Look for some adjustments to the roadway legends and stop bars.
Bear Creek Bridge- work continues on the last part of the Bear Creek Bridge, which is connected to the work on East Bolz Road approach. Look for the bridge to open later in May.
Oregon 99: work is wrapping up on the west side of Oregon 99, which mirrors the work done earlier on the east side of the highway. Watch for this construction to continue through the next several months before the new signals arrive and paving begins on OR 99 later this summer.
If you didn’t catch today’s edition of Moving Ahead with ODOT in today’s Mail Tribune, Ashland Daily Tidings and Grants Pass Daily Courier, an on line version is available at http://www.odotmovingahead.com/
Of course, there is a large section devoted to the Fern Valley project.
Stay Safe!
 
 
 

Drive It!

 

The new interchange bridge is being constructed just north of the existing bridge, leaving most roadways west of the interchange relatively untouched. The Diverging Diamond interchange design has a narrow footprint, which helps avoid touching most businesses during and after the project.
 
 

 YOUTUBE1.jpg

 Drive the partially completed interchange in 2 minutes 
 
Project Information

 Video of Luman Rd. intersection concrete pour, Feb. 6 & 7, 2016

 

 

 
​ 

 

  

 



FernValleyInterchange_December2015.jpgFernValleyInterchange_December2015.jpg

GeneralFVIDecConstruction_UpdateDec82015.pdfGeneralFVIDecConstruction_UpdateDec82015.pdf

 

 


GreenwayMap.jpg
 

Project Background

  
The $72 million Fern Valley Interchange project began in in the spring of 2014. Due to the projects size and complexity - it encompasses east and west Phoenix roadways, I-5 and Oregon 99 - the project requires more than two full construction seasons, finishing in September 2016. It also includes bike and pedestrian connections.
 
 