Text Size:   A+ A- A   •   Text Only
Find     
Site Image

I-5: Martin Creek to Anlauf Paving

Project News

Watch for intermittent lane closures after July 7
 
Although all travel lanes through the construction zone will be open during the Independence Day weekend, motorists should watch for intermittent lane closures on Interstate 5 between Drain and Cottage Grove (milepost 162-170) from July 7 to July 31.
 
Some nighttime ramp closures at Exit 162 (Drain/OR 38 junction) and Exit 163 (Curtin) will also be necessary due to paving work.
 
The southbound off-ramp at Exit 170 (south Cottage Grove) will remain closed until July 31. All northbound ramps will remain open during this construction phase.
 
Construction on the northbound lanes will begin after Labor Day and continue until mid-November.
 
For the latest road and traffic information, please visit ODOT’s travel website:  www.TripCheck.com.
 
(Updated: July 1, 2014)

Project Information

I-5Martincreektoanlaufmap.jpgOverview
This project will repair or replace much of the concrete road surface along a seven-mile section of Interstate 5 between the south Cottage Grove interchange (Exit 170) and the Oregon 38 junction (Exit 162).


Project facts

  • Location: I-5 milepost 162.2-169.2
  • Construction budget: $20 million (estimate)
  • Bid let date: April 10, 2014
  • Construction schedule: Spring 2014 to spring 2015

What is ODOT planning to do?
The seven-mile section of Interstate 5 between Martin Creek (milepost 169) and the Anlauf interchange (Exit 162) links Eugene and Cottage Grove to the Oregon 38 (Umpqua Highway) junction. The road surface in this area dates back several decades. Although it has held up remarkably well, the concrete is cracking and vulnerable to ongoing drainage problems.

At the north end of the project area, workers will dig out the existing highway to a depth of 3-4 feet, install a new rock base, and pour new 8-11” concrete travel lanes in both northbound and southbound directions. In the rest of the work zone, damaged concrete will be repaired or replaced and an additional 3” of asphalt will be paved over the road surface to protect the concrete below.

Additional work includes paving 10 interstate ramps in the project area, repairing the Oregon 38 overcrossing at the Anlauf interchange, and replacing substandard median barrier and guardrail.

Construction will begin in spring 2014 and continue until fall. Some additional work will be scheduled for spring 2015.


How will traffic be affected during construction?
I-5 traffic will be limited to one lane in each direction for most of the spring, summer and fall of 2014. Some ramp closures will be necessary.

From May to August, workers will rebuild the southbound lanes between Exit 170 (south Cottage Grove) and Exit 162 (Drain). During this time, the northbound lanes will be modified to carry one lane of traffic in each direction. Some southbound ramps will be closed.

During the fall, the process will be reversed. All traffic will be shifted into the southbound lanes, with one lane in each direction, so that workers can rebuild the northbound lanes. Some northbound ramps will be closed.

Work not completed by Thanksgiving will resume after the holiday season, when weather is favorable to construction.

Traffic impacts
ODOT will provide more information to the public and local media prior to and during construction.

For updates on construction and traffic impacts, see ODOT’s
Weekly Construction Report or visit TripCheck.com

Project Materials

NEWS RELEASE: I-5 off-ramp at Drain opens ahead of schedule.pdf (June 27, 2014)

NEWS RELEASE: I-5 ramp at Oregon 38 to close for several weeks.pdf (June 10, 2014)

INFO-SHEET-MartinCreek-2014-04-14.pdf

For More Information:



Dan Latham
ODOT Public Affairs
3500 NW Stewart Parkway
Roseburg, OR 97470
Phone: (541) 957-3601
E-mail:
Dan.Latham@odot.state.or.us