Text Size:   A+ A- A   •   Text Only
Find     
Site Image

Sunriver to Lava Butte Multi-Use Path
 
 
 
 

Current Information

Detour Map Shows Routes That Avoid Construction Activities
Construction could begin as soon as the week of February 10 on the new paved path from Sunriver to Lava Butte.  During construction, portions of existing trails or roads will be closed.  The Deschutes National Forest and the Newbery National Volcanic Monument prepared a detour map so bicyclists, pedestrians and motorist can safely avoid construction activities.  A copy of the detour map is below.
 
 
The Sunriver to Lava Butte Multi-Use Path contract was awarded to High Desert Aggregate & Paving, Inc. in December 2013.  The preliminary construction schedule follows:
 
Project begins, clearing and grubbing ​February 2014
Trail earthwork and placement of rock ​Early spring
​Paving and installation of railroad crossing protection ​Late spring, early summer
​Project completion date ​Fall 2014
 
Keep Yourself Informed
Sign up for email alerts or receive weekly updates once construction begins in February. You will be asked to set up an account, which is free and simple. The email address you provide will only be used for this project. Simply click on the envelop and sign up.

Project Components

  • Construct a 5.5-mile paved, multi-use path between Sunriver, Benham East Day Use Area and Lava Butte.
  • Install traffic and wayfinding signs along the path.
  • Install gates and flashing lights at the railroad crossing on Benham Falls Road (FS Road 9702).

Project Information Paper                                          Project Vicinity Map

Purpose and Need for the Project

Picture of existing trail between Sunriver and Lava ButteCurrently, there is not a safe, accessible way for pedestrians and bicyclists to travel between Sunriver, Benham East Day Use Area and Lava Butte. The path will create a new connection for bicyclists and pedestrians between the three tourist destinations.
 
Visitors will have the option to avoid driving to access these destinations and a new opportunity will be created to see the National Volcanic Monument from a different perspective. The path will create an accessible recreation opportunity that will allow people of all abilities to explore their National Monument.
 

Key Dates and Project Funding

Environmental Analysis Process 2012-2013
​Final Design ​2013
​Bid Let ​Fall 2013
​Construction ​2014

The estimated construction cost is $1.85 million and is being funded by the Public Lands Highways Discretionary Program and ODOT Rail Safety Program.

Contacts

Name​ ​Title ​Telephone
Number
​Email Address
​Cari Charlton ​Project Leader, ODOT ​541-388-6047 Cari.Charlton@odot.state.or.us
​Marcos Romero ​Transportation Manager, Forest Service ​541-383-5624 mromero@fs.fed.us
​Rex Holloway ​Community Liaison, ODOT ​541-388-6178 Rex.A.Holloway@odot.state.or.us