| Leaning Juniper II Wind Power Facility |
|
|
 |
|
|
Facility:
A wind energy facility with a peak generating capacity of up to 279 megawatts.
Location: Gilliam County
Status:
The Council has approved a site certificate. The facility is not yet under construction.
Certificate Holder:
Leaning Juniper Wind Power II, LLC
Contact:
Sara Parsons
Leaning Juniper Wind Power Facility
c/o PPM Energy, Inc.
1125 NW Couch St., Suite 700
Portland, OR 97209
(503) 796-7732
Department of Energy Staff: John White
Original site certificate signed: September 24, 2007
History:
- November 30, 2005: Applicant submitted a request for expedited review.
- December 15, 2005: Department of Energy approved expedited review.
- February 1, 2006: Preliminary application submitted.
- October 4, 2006: Amended preliminary application submitted.
- May 15, 2007: Application filed (complete).
- July 18, 2007: Department of Energy issued a Draft Proposed Order.
- August 9, 2007: Public hearing on Draft Proposed Order.
- August 21, 2007: Department of Energy issued a Proposed Order.
- September 21, 2007: Council approved a site certificate
- September 24, 2007: Site Certificate became effective.