Text Size:   A+ A- A   •   Text Only
Find     
Site Image

Stateline Wind Project

Facility: A wind energy facility consisting of two units. Stateline 1&2 is composed of 186 turbines and has a peak generating capacity of up to 123 megawatts. Stateline 3 consists of 43 turbines with a peak generating capacity of 99 megawatts.

Status (Operating): Stateline 1 and 2 began operation on Dec. 21, 2001 with 126 turbines, added 55 turbines on Dec. 10, 2002 and 5 more turbines on Dec. 15, 2004. Stateline 3 began operation on Dec. 16, 2009.

Location: Umatilla County, all on private land, north and east of Helix.

Certificate Holder: FPL Energy Vansycle, LLC (Stateline 1&2) and FPL Energy Stateline II, Inc. (Stateline 3).

Contact Information 

SITE CERTIFICATE HOLDER
OREGON DEPARTMENT OF ENERGY STAFF
John Goodwin, NextEra Energy Resources, Inc.
Duane Kilsdonk
P.O. Box 14000
395 E. Highland Ave.
Juno Beach, FL 33408-0420
Hermiston, OR 97838
 
To Receive Updates by E-mail:
·          To receive e-mail notices about this project, please click here.
·          To receive e-mail notices for other projects or general EFSC announcements, please go here.
 
About Oregon’s siting process:
·          For more information about Oregon’s siting process outlined in the table below, please go here.
 
Project Status (Table details will be updated as project progresses)
PROJECT PHASE DETAILS
DATE
Site certificate amendment #4: Increased site boundary and added a redesigned Stateline 3 to include 43 2.3-megawatt wind turbines. Other modifications to the site certificate included changes to the Oregon Wildlife Monitoring Plan and Re-vegetation Plan. Allowed a partial transfer of the site certificate to FPL Energy Stateline II, Inc. to construct and operate Stateline 3.
May 19, 2009
 
 
 
 
 
March 27, 2009
Site certificate amendment #3: Extended construction deadline from June 23, 2007 to Dec. 31, 2007 for Stateline 3 and modified the no-occupation agreement related to noise. (Construction deadline passed with no construction.)
July 12, 2005
 
 
 
June 20, 2005
Site certificate amendment #2: Increased the site boundary by 75 acres and added 279 turbines with electrical generation capacity of approximately 184 megawatts. Added 13 meteorological towers and other related facilities. (Described as Stateline 3.) Extended the construction deadline for 5 turbines from the Stateline 2 addition.
June 23, 2003
 
 
 
 
 
June 2, 2003
Site certificate amendment #1: Increased the site boundary by 30 acres, added 60 additional turbines and two permanent meteorological towers. (Described as Stateline 2)
May 24, 2002
 
 
May 17, 2002
Sept. 14, 2001
Oct. 23, 2001