|
|
|
|
Summit Ridge Wind Farm
|
|
|
Article Content |
 |
|
|
Facility: Wind energy facility with a peak generating capacity of approximately 200 megawatts. Location: Wasco County Status: The Council issued a site certificate for the facility. The facility is not yet under construction.
Certificate Holder: LotusWorks – Summit Ridge I, LLC Contact: Steven Ostrowski, President LotusWorks – Summit Ridge I, LLC 9611 NE 117th Ave, Suite 2840 Vancouver, WA 98662 (360) 737-9692
Department of Energy Staff: Duane Kilsdonk History:
- May 28, 2009: Applicant submitted a notice of intent.
- July 30, 2009: ODOE issued the project order.
- Sept. 30, 2009: The applicant submitted a preliminary application for site certificate.
- Nov. 30, 2009: ODOE issued a request for additional information (RAI 1).
- Jan. 19, 2010: The applicant responded to the request for additional information.
- March 8, 2010: ODOE issued a second request for additional information (RAI 2).
- March 31, 2010: The applicant responded to the second request for additional information.
- July 1, 2010: The applicant provided the final supplemental information in response to the second request for additional information.
- July 15, 2010: ODOE sends a letter detailing the final information needed to complete the application.
- July 29, 2010: The applicant provided the final information requested by ODOE in its July 15 letter.
- Aug. 24, 2010: ODOE deemed the application for site certificate complete.
- Aug. 27, 2010: ODOE issued the ASC for public comment.
- Jan. 14, 2011: ODOE issued the draft proposed order for comment.
- Feb. 4, 2011: A public hearing on the draft proposed order was held in The Dalles.
- March 4, 2011: The draft proposed order was presented to the Energy Facility Siting Council for review and comment.
- June 23, 2011: ODOE issued a proposed order and notice of contested case.
- Aug. 19, 2011: The council issued a final order and site certificate.
Documents:
|
|
|
|
|
|
|
|
|
|
|
|
|