Text Size:   A+ A- A   •   Text Only
Find     

Summit Ridge Wind Farm
Facility:
Wind energy facility with a peak generating capacity of approximately 200 megawatts.
 
Location: Wasco County
 
Status:
The Council issued a site certificate for the facility. The facility is not yet under construction.

Certificate Holder:
LotusWorks – Summit Ridge I, LLC
 
Contact:
Steven Ostrowski, President
LotusWorks – Summit Ridge I, LLC
9611 NE 117th Ave, Suite 2840
Vancouver, WA 98662
(360) 737-9692

Department of Energy Staff: Duane Kilsdonk
 
History:
  • May 28, 2009: Applicant submitted a notice of intent.
  • July 30, 2009: ODOE issued the project order.
  • Sept. 30, 2009: The applicant submitted a preliminary application for site certificate.
  • Nov. 30, 2009: ODOE issued a request for additional information (RAI 1).
  • Jan. 19, 2010: The applicant responded to the request for additional information.
  • March 8, 2010: ODOE issued a second request for additional information (RAI 2).
  • March 31, 2010: The applicant responded to the second request for additional information.
  • July 1, 2010: The applicant provided the final supplemental information in response to the second request for additional information.
  • July 15, 2010: ODOE sends a letter detailing the final information needed to complete the application.
  • July 29, 2010: The applicant provided the final information requested by ODOE in its July 15 letter.
  • Aug. 24, 2010: ODOE deemed the application for site certificate complete.
  • Aug. 27, 2010: ODOE issued the ASC for public comment.
  • Jan. 14, 2011: ODOE issued the draft proposed order for comment.
  • Feb. 4, 2011: A public hearing on the draft proposed order was held in The Dalles.
  • March 4, 2011: The draft proposed order was presented to the Energy Facility Siting Council for review and comment.
  • June 23, 2011: ODOE issued a proposed order and notice of contested case.
  • Aug. 19, 2011: The council issued a final order and site certificate.
 
Documents: