Stateline Wind Project
Facility:
Wind energy facility
Current operating capacity: 222 MW (Stateline 1&2 and Stateline 3)
 
Location: Umatilla County
 
Status:
The facility is operating. The department is accepting comments on the Stateline 3 Wildlife Monitoring Report through October 31, 2011.
 
Certificate Holders:
FPL Energy Vansycle LLC and FPL Energy Stateline II, Inc.
 
Contact:
John Goodwin
NextEra Energy Resources, Inc.
700 Universe Boulevard
P.O. Box 14000
Juno Beach, FL 33408-0420

(561) 304-5126
 
Department of Energy staff: John White 
 
Original site certificate signed: September 14, 2001
 
Current site certificate: Fourth Amended Site Certificate (effective May 19, 2009)
 
History:
  • April 27, 2000: Request for Expedited Review submitted.
  • January 11, 2001: Application submitted.
  • May 11, 2001: Application complete (date of filing).
  • July 2, 2001: Department of Energy issued a draft proposed order.
  • September 14, 2001: Council approved a site certificate.
  • September 15, 2001: Beginning of construction.
  • December 21, 2001: Beginning of operation (Stateline 1).
  • January 22, 2002: Request for Amendment #1 received.
  • April 11, 2002: Department of Energy issued a proposed order on Amendment #1.
  • May 17, 2002: Council approved Amendment #1.
  • July 1, 2002: Request for Amendment #2 received.
  • August 16, 2002: Beginning of construction (Stateline 2).
  • November 15, 2002: Revised request for Amendment #2 received.
  • December 10, 2002: Beginning of operation (Stateline 2).
  • February 11, 2003: Request for Addendum received.
  • March 25, 2003: Department of Energy issued a proposed order on Amendment #2.
  • June 6, 2003: Council approved Amendment #2.
  • March 25, 2005: Request for Amendment #3 received.
  • May 19, 2005: Department of Energy issued a proposed order on Amendment #3.
  • June 20, 2005: Council approved Amendment #3.
  • January 20, 2006: Council approved revisions to the Oregon Wildlife Monitoring Plan.
  • December 26, 2006: Request for Amendment #4 received (withdrawn).
  • October 24, 2008: Revised Request for Amendment #4 received.
  • February 20, 2009: Department of Energy issued a proposed order on Amendment #4.
  • March 27, 2009: Council approved Amendment #4.
  • May 19, 2009: Effective date of Fourth Amended Site Certificate.
  • June 9, 2009: Beginning of construction (Stateline 3).
  • November 20, 2009: Council approved an amendment of the Wildlife Monitoring and Mitigation Plan.
  • December 16, 2009: Beginning of operation (Stateline 3).
 
Documents: