OR 219 Pedestrian Safety Project

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Newberg, Yamhill County)


​​​​​​​​​Construct sidewalks to improve pedestrian safety between Aldercrest Drive and Quail Drive.


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

Use caution, there may be single lane closures with flaggers directing traffic as needed during daytime. 

Construction Impacts

​The week of Sept. 11 - Sept. 15, we're clearing trees and shrubs on OR 219 between Edgewood Drive and Sierra Vista Drive to prepare the area for our estimated construction date in 2024.

You can expect:

  • Construction crew and equipment.
  • Construction noise.
  • Occasional singe-lane closures during the day.

When construction starts, we anticipate work happening during the daytime. However there may be times when lane closures are needed and that will happen at night. We will also have a 4-5 day period where 24hr flagging will be needed so we can dig a trench across the road.

Construction Activities

We're clearing trees and shrubs in the area the week of Sept. 11.

Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not. ​​

Details

About

​We are continuing improvements on OR 219 in the City of Newberg to improve pedestrian safety. 

We are:

  • Constructing sidewalks on the west side of OR 219 by replacing the current drainage ditch with sidewalks.

  • Installing​ ADA compliant curb ramps.

  • Improving drainage.

  • Striping bike lanes on both sides of the road.​

Schedule

Design: 2020-2022
Construction may begin in spring 2024.

Location

OR 219 |

​Aldercrest Drive to Quail Drive

Cost and Funding

​$2.9 million

Contacts & Media

Project Area Map

Project Contacts

Resident Engineer - Consultant Projects
Bill Ness
Email
william.ness@odot.oregon.gov
Phone
972-304-5835

Public Information Officer
David House
Email
david.j.house@odot.oregon.gov
Phone
503-551-8641
Public Comment Form
Submit a commentfor project

Get Project Alerts

Sign up for the newsletter!

Last Updated

9/19/2023 2:15 PM

Project Number

18749