Skip to main content

Oregon State Flag An official website of the State of Oregon »

Project-Details







I-5 Rose Quarter Improvement Project

Construction Phase

Region 1: Portland metro and Hood River County (Portland, Multnomah)


​​​​​​​​​​​​​​​​​​​​​​​​​We are constructing improvements to I-5 between I-84 and I-405 in Portland. View the full project website for more information.​


Impacts

Traffic Impact

For the remainder of 2025, travelers can expect:

  • Sidewalk and lane closures on local streets near the Oregon Convention Center, including NE Oregon Street, N Interstate Ave, and NE 1st Ave, for seismic upgrades and sign structure work.
  • Occasional closures of the I-84 off-ramp to Moda Center and the Oregon Convention Center for sign structure work.  
  • Occasional nighttime lane closures and possible shoulder closures on I-5 to construct stormwater facilities.  

More traffic impacts are expected in 2026 when bridge preservation, merge lane extension, and sign structure installation work begins. To stay informed about upcoming construction and traffic impacts, sign up for email and/or text alerts.​

Meetings and Events

All project committee meetings are open to the public. If you wish to attend a virtual meeting but cannot attend by phone or computer, or you require language accommodations, please contact the project team at 503-470-3127 at least 48 hours in advance of the meeting.

We invite you to share comments by calling us at 503-470-3127. Comments received by 11 a.m. the business day before the meeting will be shared with project committee members in advance. All comments received will be added to the meeting record. 

You will also have an opportunity to provide comments during the meeting for up to two minutes by phone. ​

Schedule

The initial phase of construction (​Phase 1A) began in summer 2025 and is scheduled to conclude in late 2026.

Funding for future phases has not been secured. Construction will be sequenced to match available funding. Phase 1A provides independent utility without being dependent on the remainder of the project to proceed. 

 

Click here to enlarge the image above.​​​

Details

About

​I-5 is the main north-south route moving people and goods and connecting population centers across the West Coast of the United States from Mexico to Canada. In the Portland region between I-84 and I-405, I-5 is critical for truck freight and businesses moving goods, commuters traveling to and from Portland, and locals traveling within the region. 

The purpose of the I-5 Rose Quarter Improvement Project is to improve safety and congestion where three major interstates converge and to reconnect the Albina neighborhood through the construction of a highway cover over a portion of I-5. Project benefits, in addition those listed above, include improving safety and mobility on local streets, creating new space for community development, and developing a diverse and skilled workforce.

Detailed project information is available on the full project website.

Project Improvements​

​Phase 1A Improvements

Phase 1A includes:

  1. Stormwater improvements near the intersection of I-5 and I-405
  2. Bridge work near the intersection of I-5 and I-84
  3. Extension of the southbound auxiliary lane along I-5 between the I-84 and Morrison Bridge/OMSI exits
  4. Signage for highway cover safety and construction

Detailed construction information is available here.

​​

  

Overall Project Improvements

Phase 1A will build the southern portion of the southbound auxiliary lane between I-84 and the Morrison Bridge exit, creating more time and space for merging. It will preserve existing infrastructure and improve quality. And it will get the construction community working, building capacity for disadvantaged business enterprises and small businesses. ​

As envisioned in its entirety, the project will make travel more predictable and safer for people driving and transporting goods on I-5 between I-84 and I-405 by adding auxiliary lanes and shoulders that smooth traffic flow. The project includes a highway cover to reconnect the Historic Albina neighborhood and street improvements that will enhance safety and access for people walking, rolling, biking, riding transit and driving on local streets. The project will support the regional economy, future economic development and a more connected Albina community. Learn more here. ​

Committ​​ees

Advisory committees members' expertise reflects diverse professional backgrounds, including minority-owned firms, advocacy groups, workforce development organizations, industry associations, and community-based organizations. Some members are leaders and volunteers with strong ties to historic Albina with a wide array of civic and community interests.

The public is invited to comment at the beginning of meetings. For more information about the advisory committees, visit our Committees page

Visit our Events and Meetings page for the list of upcoming committee meetings or subscribe to our email list to receive project updates and meeting notices.​

Location

I-5 |

between the I-405 and I-84 interchanges

Cost and Funding

​The current cost estimate for the I-5 Rose Quarter Improvement Project is between $1.96 billion –$2.08 billion. This is based on a risk-based estimating process, current inflation assumptions, project schedule, and real-time market data.

The project was awarded federal Reconnecting Community and Neighborhoods grant funding in spring 2024.

Of the federal funding granted to the project, $37.5 million for design and utility relocation has been obligated for spending on the project. 

ODOT and partners – the City of Portland, Metro, Albina Vision Trust, and the Portland Trail Blazers (Rip City Management) – are committed to completing the project in its entirety. The project team is committed to rigorous risk management and real-time estimating practices to manage project costs moving forward. ​

Contractor

​Hamilton/Sundt a Joint Venture in Association with Raimore Construction LLC.

​Workforce Opportunities

Visit our Workforce Opportunities page for more information.​

Resources and Media​​

Visit our Project Library for documents related to the project and our Media page for media inquiries. ​​

Additional Information

Questions? Just ask! Call us at 503-470-3127​​

For ADA (Americans with Disabilities Act) or Civil Rights Title VI accommodations, translation services, interpretation services, or more information, call 503-731-4128 or Oregon Relay Service 7-1-1.

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.

Если вы хотите чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

如果您想瞭解這個項目,我們有提供繁體中文翻譯,請致電:503-731-4128

如果您想了解这个项目,我们有提供简体中文翻译,请致电:503-731-4128

Contacts & Media

Project logo

Project Contact

Public Outreach and Media Manager
Rose Gerber
Email
Rose.Gerber@odot.oregon.gov
Phone
503-779-6927

Last Updated

9/30/2025 8:57 AM

Project Number

19071

Project Documents

Related documents to this project
01_I5RQ_FONSI_508.pdf2024 Finding of No Significant Impact
02_I5RQ_RSEA_508.pdf2024 Revised Supplemental Environmental Assessment
03_I5RQ_SEA_508.pdf2022 Supplemental Environmental Assessment
04_I5RQ_Findings-of-Compatibility_2025.pdf2025 Findings of Compatibility
05_I5RQ_Phase_IA_Fact_Sheet_8292025.pdfAugust 2025 Phase 1A Fact Sheet
06_I5RQ_General_Factsheet_08292025.pdfAugust 2025 General Fact Sheet